Question

In: Civil Engineering

1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For...

1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For each activity, show the computed value of early start, early finish, late start, late finish, total float, and free float.

Activity Duration
mobilize 1
remove siding 4
excavate/form slab 7
place slab 4
set support beam 1
stud wall up 6
install siding 4
install windows 5
set raffers 4
install roof 6
finish trim 4
paint siding 7
move out 1

Solutions

Expert Solution


Related Solutions

Draw the schedule network diagram using Precedence Diagramming Method (PDM) and calculate Earliest Start (ES), Earliest...
Draw the schedule network diagram using Precedence Diagramming Method (PDM) and calculate Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), and Latest Finish (LF) for each activity. Activity Predecessor Duration A 2 B 3 C 3 D A 3 E D 3 F E 4 G F 3 H F 5 I G, H 6 J G 3 K H 4 L I, K 4 M J 2
Question 1 a. Draw a precedence diagram for the following fabrication of steel project. For each...
Question 1 a. Draw a precedence diagram for the following fabrication of steel project. For each activity, show the computed values of early start, early finish, late start, late finish, total float, free float and the critical path. Activity Immediate Predecessor Duration (weeks) A None 2 B A 4 C A 2 D B 2 E B, C 4 F A, E 6 G D 4 H D, E, F 2 I G, H 6 J H, F 6 K...
Given the accompanying network diagram, with times shown in days. Use Table B1 and Table B2....
Given the accompanying network diagram, with times shown in days. Use Table B1 and Table B2. a. Determine the expected duration of the project. (Round intermediate calculations to 2 decimal places and final answer to 1 decimal place.) Expected Duration             b. Compute the probability that the project will take at least 18 days. (Round intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability             Chuck’s Custom Boats (CCB) builds luxury yachts to...
The energy level diagram of the hydrogen atom is shown the figure below
The energy level diagram of the hydrogen atom is shown the figure below. An atom generally has an electron in a given energy level, however, a transition may occur if the atom absorbs or emits a photon, or particle of light.Note: The energy of a photon can be written as \(E_{v}=h c / \lambda\) and the constants \(h c=1240 \mathrm{eV}-\mathrm{nm}\).1. In the Bohr model of the atom, energy is radiated whenA. an electron falls from an outer energy level to...
The structures of carbon dioxide and silicon dioxide are shown in the diagram below.
The structures of carbon dioxide and silicon dioxide are shown in the diagram below. Use your knowledge of structure and bonding to explain the following: a. Carbon dioxide is a gas at room temperature. b. Silicon(IV) oxide is a solid with a high melting point. c. Neither carbon dioxide nor silicon(IV) oxide conducts electricity.
The diagram of a eukaryotic ribosome shown below contains several errors
The diagram of a eukaryotic ribosome shown below contains several errors Part A Examine the diagram carefully, and identify each error. Select all that apply. the number of ribosomal subunits is incorrect the ribosome is moving in the wrong direction along the MRNA the amino acid on the tRNA in the A site is incorrect the terminal amino acid of the peptide is incorrect the MRNA incorrectly contains Ts the MRNA incorrectly contains adenines small ribosomal subunit size is incorrect the amino acids on the tRNA in the P site...
1. Describe the basic components of network security and the differences between wired and wireless network...
1. Describe the basic components of network security and the differences between wired and wireless network security best practices.
The process flow diagram for an office chair is shown below. There are three steps on...
The process flow diagram for an office chair is shown below. There are three steps on a worker-paced line, and no inventory is stored between the steps. The processing times are: Base: 6 minutes/unit Upholstery: 10 minutes/unit Assembly: 8 minutes/unit Demand rate is 7 units/hour. What is the resource utilization at each unit? (Assume that there is sufficient input for the process). Resource Utilization = Flow Rate/ resource capacity Raw material - Base (6min/ unit)- upholstery (10 min/unit) - assembly...
The sketch below is a free-body diagram (with all the forces shown) of a bridge. The...
The sketch below is a free-body diagram (with all the forces shown) of a bridge. The distance are each 800 cm along the bottome of the bridge, "RL" to "A", "A" to "C", "C" to "B" and "B" to "R". The vertical height shown on the right side of the sketch is 1385 cm. The known forces are A= 5000 N, B= 3000 N and C= 10,000 N. You are to calculate the unknown reactions RLx, RLy and Rr.   
Write a C program to create a series of processes, as shown below in the diagram....
Write a C program to create a series of processes, as shown below in the diagram. P |------ ---- > c1 |------------>c2                              |------- ------>c3 ---------->c4                             In other words, the parent process p creates process c1, c1 creates c2 and c3, and c3 creates c4. A sample run of the program shows Your program should output something similar to what is shown above. You could optionally use wait/waitpid/sleep/exit in your program. Comment your code to show where you created...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT