Question

In: Operations Management

A project for improving a billing process has the following precedence relationships and activity​ times: Using...

A project for improving a billing process has the following precedence relationships and activity​ times: Using the info below calculate the slack for each activity. Which activities are on the critical path?                                                                                                          

Activity

Activity Time​ (weeks)

Immediate​ Predecessor(s)

A

5

----

B

10

-----

C

6

A

D

14

​B, C

E

9

B

F

5

D

G

3

E

H

6

​F, G

Solutions

Expert Solution

Computation of earliest starting and finishing times is aided by two simple rules:
1. The earliest finish time for any activity is equal to its earliest start time plus its expected
duration, t:
EF = ES + t
2. ES for activities at nodes with one entering arrow is equal to EF of the entering arrow. ES
for activities leaving nodes with multiple entering arrows is equal to the largest EF of the
entering arrow.
Computation of the latest starting and finishing times is aided by the use of two rules:
1. The latest starting time for each activity is equal to its latest finishing time minus its
expected duration:
LS = LF - t
2. For nodes with one leaving arrow, LF for arrows entering that node equals the LS of the
leaving arrow. For nodes with multiple leaving arrows, LF for arrows entering that node
equals the smallest LS of leaving arrows.
Finding ES and EF times involves a forward pass through the network; finding LS and LF
times involves a backward pass through the network. Hence, we must begin with the EF of the
last activity and use that time as the LF for the last activity. Then we obtain the LS for the last
activity by subtracting its expected duration from its LF
Slack = LS-ES = LF-EF
Activities for which Slack = 0 are in critical path

Expected time ES EF LS LF Slack On Critical Path
A 5 0 5 0 5 0 Yes
B 10 0 10 1 11 1 No
C 6 5 11 5 11 0 Yes
D 14 11 25 11 25 0 Yes
E 9 10 19 18 27 8 No
F 5 25 30 25 30 0 Yes
G 3 19 22 27 30 8 No
H 6 30 36 30 36 0 Yes

Related Solutions

A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
Problem #4 PERT Analysis: Consider the project with the following estimates for activity times and precedence...
Problem #4 PERT Analysis: Consider the project with the following estimates for activity times and precedence relationships (be sure to use the triple time estimate). All times are in days: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 6 --- B 5 7 10 --- C 2 3 11 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path project durations. Determine the critical path and the expected project completion time. Find the...
You are the manager of a project to improve the billing process at your firm. The...
You are the manager of a project to improve the billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1600 per week, and penalty costs are $1200 per week after week 12. a- What is the minimum-cost schedule for this project? b- What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
Question 1 a. Draw a precedence diagram for the following fabrication of steel project. For each...
Question 1 a. Draw a precedence diagram for the following fabrication of steel project. For each activity, show the computed values of early start, early finish, late start, late finish, total float, free float and the critical path. Activity Immediate Predecessor Duration (weeks) A None 2 B A 4 C A 2 D B 2 E B, C 4 F A, E 6 G D 4 H D, E, F 2 I G, H 6 J H, F 6 K...
Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS,...
Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS, LF, TF and FF for each activity. Which activities in the project are on the critical path Activity Duration IPA Type of relationship Lag A 4 B 3 C 8 A D 7 A, B E 6 D SS 3 F 3 D G 5 F SS FF 2 Note: If the relationship type is not mentioned, it is FS. If no lag/lead is...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT