In: Operations Management
What is the critical path?
What is the EF for the project to obtain financing?
What is the ES for the Legal work?
What is the total duration of the entire project?
What is the LF for creating the financing plan?
What is the LS for Detailed Engineering (2/2)?
What is the Float for the accounting activity?
What is the EF for commissioning and transfer?
What is the LF for commissioning and transfer?
What is the ES for the Finish Construction activity?
What is the EF for the Detailed Engineering (1/2) activity?
What is the Float for the Drawing activity?
How many critical paths are there?
What is LS for Begin Construction?
assume # represent activity number and name respectively . |
for example, shareholder meeting is considered to be activity 1 i.e. shareholder meeting |
During forward pass, maximum time (early finish) will be considered in case of of more than one predecessor to calculate the early start.
During backward pass, the minimum time (late start) will be considered in case of more than one predecessor to calculate the lat start
What is the critical path? | 2-4-7-9-11-14 | activities whose slack is 0 |
What is the EF for the project to obtain financing? | 6 | |
What is the ES for the Legal work? | 11 | |
What is the total duration of the entire project? | 21 | |
What is the LF for creating the financing plan? | 5 | |
What is the LS for Detailed Engineering (2/2)? | 8 | |
What is the Float for the accounting activity? | 4 | |
What is the EF for commissioning and transfer? | 20 | |
What is the LF for commissioning and transfer? | 21 | |
What is the ES for the Finish Construction activity? | 11 | |
What is the EF for the Detailed Engineering (1/2) activity? | 7 | |
What is the Float for the Drawing activity? | 1 | |
How many critical paths are there? | 1 | |
What is LS for Begin Construction? | 7 |