Question

In: Operations Management

What is the critical path?What is the EF for the project to obtain financing?What...

11 14 Shareholder Project Termination Create Obtain financing Accounting Legal financing plan meeting 2 2 3 2 4 12 Project ou

What is the critical path?

What is the EF for the project to obtain financing?

What is the ES for the Legal work?

What is the total duration of the entire project?

What is the LF for creating the financing plan?

What is the LS for Detailed Engineering (2/2)?

What is the Float for the accounting activity?

What is the EF for commissioning and transfer?

What is the LF for commissioning and transfer?

What is the ES for the Finish Construction activity?

What is the EF for the Detailed Engineering (1/2) activity?

What is the Float for the Drawing activity?

How many critical paths are there?

What is LS for Begin Construction?


Solutions

Expert Solution

assume # represent activity number and name respectively .
for example, shareholder meeting is considered to be activity 1 i.e. shareholder meeting

During forward pass, maximum time (early finish) will be considered in case of of more than one predecessor to calculate the early start.

During backward pass, the minimum time (late start) will be considered in case of more than one predecessor to calculate the lat start

What is the critical path? 2-4-7-9-11-14 activities whose slack is 0
What is the EF for the project to obtain financing? 6
What is the ES for the Legal work? 11
What is the total duration of the entire project? 21
What is the LF for creating the financing plan? 5
What is the LS for Detailed Engineering (2/2)? 8
What is the Float for the accounting activity? 4
What is the EF for commissioning and transfer? 20
What is the LF for commissioning and transfer? 21
What is the ES for the Finish Construction activity? 11
What is the EF for the Detailed Engineering (1/2) activity? 7
What is the Float for the Drawing activity? 1
How many critical paths are there? 1
What is LS for Begin Construction? 7

Related Solutions

Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
What is the critical path of the network?
What is the critical path of the network?
In managing a project of the scale and type indicated below, the Critical path method(CPM) is...
In managing a project of the scale and type indicated below, the Critical path method(CPM) is utilized, composed of the following activities and their durations. Activity Time in days preceding activities A 10 -- B 6 -- C 8 A D 3 B E 7 C G 12 B H 5 C F 3 D, G I 5 E, H J K 8 8 C F, I, J a) Draw a critical path network(CPM) network diagram for this project on...
Consider the project described in the below Excel a. Use Excel to find the critical path...
Consider the project described in the below Excel a. Use Excel to find the critical path and the project duration using normal activity times. b. What is the shortest duration the project can be crashed down to? c. If you were to crash the project manually and your goal is to minimize crashing cost, which activity would you start with? d. Find the cheapest way to crash the project to 33 weeks. What are the critical activities in the crashed...
All of the following are true about project schedule EXCEPT? Select one: a. Critical path is...
All of the following are true about project schedule EXCEPT? Select one: a. Critical path is the shortest path in the network b. Activities on critical path have slack time of zero c. To shorten the project completion time, activities on the critical path should be crashed. d. The project completion time is the sum of all activity times on the critical path.
Question 1: Compare and contrast the project evaluation and review technique (PERT) with the critical path...
Question 1: Compare and contrast the project evaluation and review technique (PERT) with the critical path method (CPM). Question 2: Explain in detail Eliyahu Goldratt’s Theory of Constraints with a brief note on its application in Project Management.
Project Scheduling (incl. Network, Critical Path, WBS) Project: opening a new Restaurant. Anyone know how to...
Project Scheduling (incl. Network, Critical Path, WBS) Project: opening a new Restaurant. Anyone know how to create a critical path and wbs for this project? I did the network but I am not sure if I did it right.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT