Question

In: Accounting

On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...

On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19 Contract costs incurred to date $  300,000 $1,200,000 $2,100,000 Estimated costs to complete the contract  1,200,000    800,000 -0- Billings to Gumbel    300,000  1,100,000  1,850,000 Instructions (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.)

Solutions

Expert Solution


Related Solutions

On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Skysong estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Headland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
Problem 18-11 On July 1, 2017, Vaughn Construction Company Inc. contracted to build an office building...
Problem 18-11 On July 1, 2017, Vaughn Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Vaughn estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18...
Problem 18-11 On July 1, 2017, Nash Construction Company Inc. contracted to build an office building...
Problem 18-11 On July 1, 2017, Nash Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Nash estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18...
On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp
Construction Contract Accounting as per Percentage-of-Completion Method & Completed Contract Method.  Problem Four: Long-Term Contract  On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp. for a total contract price of S2,000,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022: At At At 12/31/2020 12/31/2021 12/31/2022 Contract...
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin...
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin on January 1, 2020, and the estimated time of completion is July 1, 2023. The building cost is estimated to be $20,000,000 and will be billed at $24,000,000. The following data relate to the construction period: 2020 2021 2022 2023 Cost to date 5,500,000 10,000,000 13,500,000 20,000,000 Estimated cost to complete 14,500,000 10,000,000 6,500,000 -0- Progress billings to date 3,000,000 9,000,000 14,000,000 24,000,000 Cash...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT