In: Accounting
Problem 18-11
On July 1, 2017, Nash Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Nash estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019.
At |
At |
At |
||||
Contract costs incurred to date | $312,900 | $1,148,400 | $2,076,000 | |||
Estimated costs to complete the contract | 1,177,100 | 831,600 | –0– | |||
Billings to Gumbel | 300,000 | 1,090,000 | 1,850,000 |
(a) Using the percentage-of-completion method,
prepare schedules to compute the profit or loss to be recognized as
a result of this contract for the years ended December 31, 2017,
2018, and 2019. (Ignore income taxes.) (If answer is 0,
please enter 0. Do not leave any field blank. Enter negative
amounts using either a negative sign preceding the number e.g. -45
or parentheses e.g. (45).)
Computation of Recognizable Profit/Loss Completed-Contract Method: | |
2017 | none |
2018 | |
Cost to date 31-12-2018 | 1,148,400 |
estimated cost to complete | 831,600 |
Estimated total cost | 1,980,000 |
Deduct contract price | 1,890,000 |
Profit to be recognized in 2018 | 90,000 |
2019 | |
Total costs recognized | 2,076,000 |
Total revenue recognized | 1,890,000 |
Total Profit on contract | 186,000 |
Deduct profit recognized in 2018 | 90,000 |
Profit recognized in 2019 | 96,000 |