Question

In: Accounting

On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp

Construction Contract Accounting as per Percentage-of-Completion Method & Completed Contract Method.

 Problem Four: Long-Term Contract

 On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp. for a total contract price of S2,000,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gabriella for 2020, 2021, and 2022.

 Required:

 a. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022.

 b. Using the completed-contract method, how much profit or loss will be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022.

 

 

Solutions

Expert Solution

Under the Percentage of Completion Method, costs and revenues are recognized for the period based on the stage of completion of the construction process.
 
2020
2021
2022
Cost to date (A)
$300,000
$600,000
$1,000,000
Estimated cost to complete (B)
$1,200,000
$400,000
$0
Total Estimated Cost of Project (C= A+B)
$1,500,000
$1,000,000
$1,000,000
Percentage completion (A/C)
20%
60%
100%
Revenue recognized (D)
$400,000
$1,200,000
$2,000,000
Gross Profit (D-A)
$100,000
$600,000
$1,000,000
Profit recognized in previous year
-$0
-$100,000
-$600,000
Profit (loss) this year
$100,000
$500,000
$400,000
** Revenue Recognized is equal to (Percentage of Completion x Contract Price)
where, contract price is given to be $2,000,000.
 
 
 
In Completed Contract Method, all revenues and expenses incurred are deferred to the end of the construction period where the construction process is completed.
 
Only in 2022, will the revenues and expenses be recorded.
 
2020
2021
2022
Cost to date (A)
$0
$0
$1,000,000
Estimated cost to complete
$0
$0
$0
Percentage completion
0
0
100%
Revenue recognized (B)
$0
$0
$2,000,000
Gross Profit (B - A)
$0
$0
$1,000,000

Year-End Profits Recognized
 
2020
2021
2022
Percentage of Completion Method
$100,000
$500,000
$400,000
Completed-Contract Method
 
 
$1,000,000

Related Solutions

On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Skysong estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Headland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022: At At At 12/31/2020 12/31/2021 12/31/2022 Contract...
Problem 18-11 On July 1, 2017, Vaughn Construction Company Inc. contracted to build an office building...
Problem 18-11 On July 1, 2017, Vaughn Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Vaughn estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18...
Problem 18-11 On July 1, 2017, Nash Construction Company Inc. contracted to build an office building...
Problem 18-11 On July 1, 2017, Nash Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Nash estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18...
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin...
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin on January 1, 2020, and the estimated time of completion is July 1, 2023. The building cost is estimated to be $20,000,000 and will be billed at $24,000,000. The following data relate to the construction period: 2020 2021 2022 2023 Cost to date 5,500,000 10,000,000 13,500,000 20,000,000 Estimated cost to complete 14,500,000 10,000,000 6,500,000 -0- Progress billings to date 3,000,000 9,000,000 14,000,000 24,000,000 Cash...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31,2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below.                                                                                                                                                                                    2020                                    2021                      2022 Contract costs incurred during the year                            $3,400,000            $2,400,000          $2,900,000 Estimated costs to complete the contract at Dec 31          ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT