In: Accounting
Construction Contract Accounting as per Percentage-of-Completion Method & Completed Contract Method.
Problem Four: Long-Term Contract
On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp. for a total contract price of S2,000,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gabriella for 2020, 2021, and 2022.
Required:
a. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022.
b. Using the completed-contract method, how much profit or loss will be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022.
|
2020
|
2021
|
2022
|
Cost to date (A)
|
$300,000
|
$600,000
|
$1,000,000
|
Estimated cost to complete (B)
|
$1,200,000
|
$400,000
|
$0
|
Total Estimated Cost of Project (C= A+B)
|
$1,500,000
|
$1,000,000
|
$1,000,000
|
Percentage completion (A/C)
|
20%
|
60%
|
100%
|
Revenue recognized (D)
|
|
|
|
Gross Profit (D-A)
|
|
|
|
Profit recognized in previous year
|
-$0
|
-$100,000
|
-$600,000
|
Profit (loss) this year
|
|
|
|
|
2020
|
2021
|
2022
|
Cost to date (A)
|
$0
|
$0
|
$1,000,000
|
Estimated cost to complete
|
$0
|
$0
|
$0
|
Percentage completion
|
0
|
0
|
100%
|
Revenue recognized (B)
|
$0
|
$0
|
$2,000,000
|
Gross Profit (B - A)
|
$0
|
$0
|
$1,000,000
|
Year-End Profits Recognized
|
|||
|
2020
|
2021
|
2022
|
Percentage of Completion Method
|
$100,000
|
$500,000
|
$400,000
|
Completed-Contract Method
|
|
|
$1,000,000
|