Question

In: Accounting

On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily...

On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:

At

At

At

12/31/2020

12/31/2021

12/31/2022

Contract costs incurred during the year

$   600,000

$ 1,500,000

$ 2,750,000

Estimated costs to complete the contract

   1,800,000

      1,200,000

                    -  

Billings to Sicily

       400,000

      1,200,000

     2,400,000

Instructions:

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a

result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of

this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

Solutions

Expert Solution

Answer :

(a) Using the percentage-of-completion method :

Particulars 2020 2021 2022
Cumulative Cost Incurred at year End 600,000 1,500,000 2,750,000
Estimated Costs to complete the contract 1,800,000 1,200,000
Total Costs 2,400,000 2,700,000 2,750,000
% of Completion = Cost Incurred / Total Costs 25.00% 55.56% 100.00%
Cost Incurred during the year 600,000 900,000 1,250,000
Particulars 2020 2021 2022
Revenue recognized = 2,600,000 x % of Completion 650,000 1,444,444 2,600,000
Less : Revenue recognized in earlier years 0 650,000 1,444,444
Revenue recognized in current Year 650,000 794,444 1,155,556
Less : Cost Incurred during the year 600,000 900,000 1,250,000
Gross Profit (Loss) during the year 50,000 (105,556) (94,444)

So,

Particulars Amount
Gross Profit (Loss) during the year 2020 $50,000
Gross Profit (Loss) during the year 2021 ($105,556)
Gross Profit (Loss) during the year 2022 ($94,444)

(b) Using the completed-contract method :

Particulars Amount
Gross Profit (Loss) during the year 2020 $0
Gross Profit (Loss) during the year 2021 $0
Gross Profit (Loss) during the year 2022 ($150,000)

Related Solutions

On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp
Construction Contract Accounting as per Percentage-of-Completion Method & Completed Contract Method.  Problem Four: Long-Term Contract  On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp. for a total contract price of S2,000,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated...
On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Skysong estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Headland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin...
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin on January 1, 2020, and the estimated time of completion is July 1, 2023. The building cost is estimated to be $20,000,000 and will be billed at $24,000,000. The following data relate to the construction period: 2020 2021 2022 2023 Cost to date 5,500,000 10,000,000 13,500,000 20,000,000 Estimated cost to complete 14,500,000 10,000,000 6,500,000 -0- Progress billings to date 3,000,000 9,000,000 14,000,000 24,000,000 Cash...
Problem 18-11 On July 1, 2017, Vaughn Construction Company Inc. contracted to build an office building...
Problem 18-11 On July 1, 2017, Vaughn Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Vaughn estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18...
Problem 18-11 On July 1, 2017, Nash Construction Company Inc. contracted to build an office building...
Problem 18-11 On July 1, 2017, Nash Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Nash estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31,2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below.                                                                                                                                                                                    2020                                    2021                      2022 Contract costs incurred during the year                            $3,400,000            $2,400,000          $2,900,000 Estimated costs to complete the contract at Dec 31          ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT