about critical path of a project network is that, A. the
critical path is the shortest of all paths through the network B.
the critical path is the set of activities that has no slack time
C. the critical path is that set of activities that has no positive
slack time D. some networks may not have any critical path
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
Project Scheduling (incl. Network, Critical Path, WBS)
Project: opening a new Restaurant.
Anyone know how to create a critical path and wbs for this
project? I did the network but I am not sure if I did it right.
For the following network determine:
a) The activities on the critical path
b) The time for the critical path
c) The slack for EVERY activity
Activity
Immediate Predecessors
Time
A
-
5
B
-
4
C
A,B
3
D
A,B
6
E
A,B
2
F
C,D,E
8
G
C,D,E
5
Find the critical path and critical time for the
following business network:
Activity Pre. Act. Duration
A - 18
B A 25
C B 1
D C 14
E C 12
F E 1
G D 18
H E,G 3
I C 14
J F,I 16
K J 5
L J 25
M H 22
N K,L 13