In: Operations Management
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
B. the critical path is the set of activities that has no slack time
The critical path is the longest path which has no slack time. All the activities must be done for the completion of the task.