All of the following are true about project schedule EXCEPT?
Select one:
a. Critical path is the shortest path in the network
b. Activities on critical path have slack time of zero
c. To shorten the project completion time, activities on the critical path should be crashed.
d. The project completion time is the sum of all activity times on the critical path.
a. Critical path is the shortest path in the network
The critical path is the network that covers all the activities that are critical towards the completion of the project accordingly.