In managing a project of the scale and type indicated below, the Critical path method(CPM) is...

In managing a project of the scale and type indicated below, the Critical path method(CPM) is utilized, composed of the following activities and their durations.

Activity Time in days preceding activities
A 10 --
B 6 --
C 8 A
D 3 B
E 7 C
G 12 B
H 5 C
F 3 D, G
I 5 E, H

J

K

8

8

C

F, I, J

a) Draw a critical path network(CPM) network diagram for this project on a separate sheet.

b) Calculate the Early and Late statistics for each activity with their associate slacks.

c) Identify the critical path.

d) Specify the project duration.

e) How long can activities namely:

i) D be delayed without delaying the project completion time?

ii) H be delayed without delaying the project completion time?

iii) J be delayed without delaying the project completion time?

Solutions

Expert Solution

The Critical Path Method (CPM) Network Diagram is as below :

Now, we tabulate the activities and the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS) and Latest Finish (LF) and calculate the slack as below :

Questions A & B are answered above. Now, using the above table, we answer the rest of the questions :

C) Critical Path is the longest path in the network and contains activities with zero slack. So we can infer that the Critical Path is A-C-E-I-K and the duration of the critical path is 10+8+7+5+8 = 38

D) The Project Duration is 38 days

E) The Slack determines how long the activities can be delayed without delaying the project completion time..

Ei) D can be delayed by 18 days

Eii) H can be delayed by 2 days

Eiii) J can be delayed by 4 days


Related Solutions

The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
PERT and CPM techniques work by determining the "critical path" for the completion of a series...
PERT and CPM techniques work by determining the "critical path" for the completion of a series of interrelated activities. True or False? When there is a lack of specifications, service-oriented architecture (SOA) is preferred to SDLC for designing a system. True or False? Planning is the last phase of the SDLC process. True or False?
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Consider the project described in the below Excel a. Use Excel to find the critical path...
Consider the project described in the below Excel a. Use Excel to find the critical path and the project duration using normal activity times. b. What is the shortest duration the project can be crashed down to? c. If you were to crash the project manually and your goal is to minimize crashing cost, which activity would you start with? d. Find the cheapest way to crash the project to 33 weeks. What are the critical activities in the crashed...
4.) You are managing a task on the critical path which has a BAC of $500,000....
4.) You are managing a task on the critical path which has a BAC of $500,000. The task is 80 percent complete. The team has completed 10 weeks on the task, and it was scheduled to take 10 weeks. You have spent $400,000 on the task so far. Calculate the cost performance index (CPI) and schedule performance index (SPI). Briefly explain what the reults mean.
What are the limitations of Graphic Rating Scale Method,Scale for Alternate Ranking and Critical Incident Method...
What are the limitations of Graphic Rating Scale Method,Scale for Alternate Ranking and Critical Incident Method based on HRM?
What is the critical path?What is the EF for the project to obtain financing?What...
What is the critical path?What is the EF for the project to obtain financing?What is the ES for the Legal work?What is the total duration of the entire project?What is the LF for creating the financing plan?What is the LS for Detailed Engineering (2/2)?What is the Float for the accounting activity?What is the EF for commissioning and transfer?What is the LF for commissioning and transfer?What is the ES for the Finish Construction activity?What is the EF for the Detailed Engineering...
Given the data in the spreadsheet below, what is the probability of completing the critical path...
Given the data in the spreadsheet below, what is the probability of completing the critical path of the project in 34 or more time units? Activity Preceded By Optimistic Time Most Likely Time Pessimistic Time A None 12.89 15.25 18.21 B None 14.17 15.61 18.13 C A and B 12.33 14.2 17.98 D A and B 14.84 17.64 20.53
In the Critical Path Method network diagram, what is unique about the early start and early...
In the Critical Path Method network diagram, what is unique about the early start and early finish date of each node on the critical path?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT