Question

In: Operations Management

What is the critical path of the network?

What is the critical path of the network?

Solutions

Expert Solution

      Critical means something very important. Hence, critical path of a network means a series of well-defined instructions or steps for achieving a pre-defined target within the available time frame. It is determined by taking into account the longest time frame that can finish an activity or a project and how can one complete all the tasks by reducing the time duration, without compromising with the quality of work being done or performed.

       The concept of critical path is not so new but has its roots going back to 1950s. This concept is very useful in managing any project and saving time. If any of the activities being placed in the series of critical path change, it can immensely affect the end date of the completion of the project. The entire project is divided into smaller activities with a defined target and time frame. A network schedule of all the defined activities needs to be prepared.

        The critical path works on the principle of early start means early finish i.e. ‘Early start + Duration = Early finish’, where early start means the earliest time of starting of an activity, duration means the time taken to complete that activity and early finish means the earliest end to the activity being performed. Even after taking care of a number of aspects, it is possible that the work is not started on the right time. To avoid this last minute problem, another plan with ‘Late start + Float = Late finish’ is prepared, which lays down the latest time at which the project can be started, float means the time by which the activity would be delayed and late finish represents the latest time at which the activity would be finished.

          Cost, time and quality are integral components of the critical path of network. It is possible that an activity has more activities underlying in it. In order to move to the next step, it is important to complete these activities first. Any delay or avoidance of these activities will directly lead to delay in the completion of the project.

An example to understand this concept can be the building of a house. The first step would be to dig foundation which could take up to 8 days, followed by building of walls which can take 10 days, followed by building of roof which can take 9 days. The critical path will include 27 days but if windows are to be made and fixtures are to be installed which can take 5 days, these work can be done during the last stage of completion. Hence, these can be done in the last 4-5 days without increasing the time frame of 27 days. This is because the critical path is being identified as building of house with four walls and roof.


Related Solutions

Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Build the network and determine the critical path.
Build the network and determine the critical path.
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
In the Critical Path Method network diagram, what is unique about the early start and early...
In the Critical Path Method network diagram, what is unique about the early start and early finish date of each node on the critical path?
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration A - 18 B A 25 C B 1 D C 14 E C 12 F E 1 G D 18 H E,G 3 I C 14 J F,I 16 K J 5 L J 25 M H 22 N K,L 13
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
What is the critical path?What is the EF for the project to obtain financing?What...
What is the critical path?What is the EF for the project to obtain financing?What is the ES for the Legal work?What is the total duration of the entire project?What is the LF for creating the financing plan?What is the LS for Detailed Engineering (2/2)?What is the Float for the accounting activity?What is the EF for commissioning and transfer?What is the LF for commissioning and transfer?What is the ES for the Finish Construction activity?What is the EF for the Detailed Engineering...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT