In: Operations Management
Project Scheduling (incl. Network, Critical Path, WBS)
Project: opening a new Restaurant.
Anyone know how to create a critical path and wbs for this project? I did the network but I am not sure if I did it right.
activity | Description | Predecessor | Duration |
A | Identifying place | None | 1 |
B | Identifying budget | None | 1 |
C | Renting the place | A,B | 3 |
D | Preparation of blueprint of facility | C,F | 2 |
E | Engaging interior designer | D | 1 |
F | Applying for registration and getting it done | C | 4 |
G | Get the interiors done for dining area | E | 6 |
H | Contract with utilites provider | D | 2 |
I | Purchase the machinery and equipments for kitchen | D | 1 |
J | Installation of kitchen | I | 2 |
K | Plumbing, Air conditioning and other works done | H | 3 |
L | Get a final finishing touch | J,G,K | 2 |
M | Hire the staff | C | 5 |
N | Train the staff | M | 2 |
O | Inaugurate the facility | N,L | None |
WBS
Pre requisites -
Identifying place |
Identifying budget |
Renting the place |
2. Formalities
Applying for registration and getting it done |
3. Initiation
Preparation of blueprint of facility |
4. Preparing kitchen
Contract with utilites provider |
Purchase the machinery and equipments for kitchen |
Installation of kitchen |
Plumbing, Air conditioning and other works done |
5. Hiring and training manpower
Hire the staff |
Train the staff |
6. Getting interiors done
Engaging interior designer |
Get the interiors done for dining area |
7. Finshing up
Get a final finishing touch |