Question

In: Operations Management

Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...

Activity Code

Immediate Predecessors

Activity Duration (Week)

A

None

3

B

A

3

C

A

2

D

C

2

E

B&C

3

F

B

2

G

D&E

1

H

G

4

I

F

7

J

H&I

2

K

J

4

L

F

6

Activity Code

Early Start

Early Finish

Late start

Later Finish

Total Float

A

0

3

0

3

0

B

3

6

3

6

0

C

3

5

5

7

2

D

5

7

8

10

3

E

6

9

7

10

1

F

6

8

6

8

0

G

9

10

10

11

1

H

10

14

11

15

1

I

8

15

8

15

0

J

15

17

15

17

0

K

17

21

17

21

0

L

8

14

15

21

7

the Critical Path is A-B-F-I-J-K=21    

1-)If all critical path activities were crashed by 25%, calculate the new overall project duration?

Solutions

Expert Solution

Activity Code Reduced Duration Early Start Early Finish Late start Later Finish Total Float
A 2.25 0 2.25 0 2.25 0
B 2.25 2.25 4.5 2.25 4.5 0
C 2 2.25 4.25 2.5 4.5 0.25
D 2 4.25 6.25 5.5 7.5 1.25
E 3 4.5 7.5 4.5 7.5 0
F 1.50 4.5 6 5.75 7.25 1.25
G 1 7.5 8.5 7.5 8.5 0
H 4 8.5 12.5 8.5 12.5 0
I 5.25 6 11.25 7.25 12.5 1.25
J 1.50 12.5 14 12.5 14 0
K 3 14 17 14 17 0
L 6 6 12 11 17 5

So,

After reducing all the critical path activities by 25%, a new critical path emerges i.e. A-B-E-G-H-J-K.

The project duration will be 17 weeks


Related Solutions

Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity...
1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A, B, and C are week 5, week 7, and week 4, what are the EST and EFT for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input EST in the first blank and EFT in the second blank.) 2)In a project, activity A, B, and C are the successors...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
Activity Duration(hours) Depends on : Numbers of workers A 5 4 B 2 2 C 4...
Activity Duration(hours) Depends on : Numbers of workers A 5 4 B 2 2 C 4 5 D 6 A,B 1 E 2 A,B,C 6 F 2 B,C 3 G 5 F 4 H 8 E,F 2 I 3 G 7 J 5 H,I 3 K 6 J 4 L 8 I 3 Calculate a lower bound for the number of workers required to complete the project in 26 days. [2 ????] Use the precedence table to draw an activity-on-arc...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors Predecessors: A is none B is none C is B D is A & C E is B F is D, E, G G is B H is F I is G J is I What is slack time (float) for A6 weeks---B6 weeks---C5 weeks D4 weeks, E5 weeks F7 weeks, G4 weeks H8 weeks I5 weeks J3 weeks Step 1: Construct a network...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT