Question

In: Operations Management

Activity Duration(hours) Depends on : Numbers of workers A 5 4 B 2 2 C 4...

Activity Duration(hours) Depends on : Numbers of workers
A 5 4
B 2 2
C 4 5
D 6 A,B 1
E 2 A,B,C 6
F 2 B,C 3
G 5 F 4
H 8 E,F 2
I 3 G 7
J 5 H,I 3
K 6 J 4
L 8 I 3
  1. Calculate a lower bound for the number of workers required to complete the project in 26 days. [2 ????]
  2. Use the precedence table to draw an activity-on-arc network. Include the early and late times for each event. [8 ?????]
  3. Which activities are critical [2 ?????]?
  4. Find the critical path for the network. [2 ?????]
  5. Calculate the float of each activity [6 ?????]
  6. What is the total float activity? [3 ?????]
  7. Draw a Cascade (Gantt) charts to represent the project [5 ?????]
  8. . It is possible for 4 workers to complete activity C in 5 hours. [2 ?????]
  9. Would you recommend this approach? Fully explain your answer. [2 ?????]

Solutions

Expert Solution

Answer:

a. As per given information, the longest chain of activities will take 26 hours with the allocated no. of workers, i.e. 44 no. The question reads as “number of workers required to complete the project in 26 days”. Is it 26 days? If so, then only one worker would be able to complete the job within such time frame. And if it is 26 hours, then workers have to be engaged phase by phase for set of activities which could be simultaneously operated.

Here the longest track is E-H-J and F-G-I-J. The maximum no, of allocation at any activity within this path are 6 and 7 respectively. Therefore, minimum 13 worker can perform the job by doing continuously.

b. The Network Diagram

Table of event timing

Activity

Duration (hours)

Depends on :

Numbers of workers

Early Time

Late Time

A

5

4

5

5

B

2

2

2

2

C

4

5

4

4

D

6

A,B

1

11

13

E

2

A,B,C

6

7

13

F

2

B,C

3

6

8

G

5

F

4

11

13

H

8

E,F

2

15

21

I

3

G

7

14

16

J

5

H,I

3

20

26

K

6

J

4

26

32

L

8

I

3

22

24

c. The critical activities are:

A – E – H – J – K

The activities have longest overall duration. Together these activities define the minimum required time to complete the entire project, as the other activities can be accomplished simultaneously beside these specific activities.

d. Critical path is already marked in red color in the above diagram.


Related Solutions

Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 Calculate the probability of completing the project between 35 and 40 weeks? [4 pts]    f Answer the project manager’s question:...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2 G D&E 1 H G 4 I F 7 J H&I 2 K J 4 L F 6 Activity Code Early Start Early Finish Late start Later Finish Total Float A 0 3 0 3 0 B 3 6 3 6 0 C 3 5 5 7 2 D 5 7 8 10 3 E...
A = [4, 5, 9] B = [-4, 5, -7] C = [2, -7, -8, 5]...
A = [4, 5, 9] B = [-4, 5, -7] C = [2, -7, -8, 5] D = [1, -9, 5, -3] E = [3, 3, -1] Uz = 1/|z| ^z d(X,Y) = (Rθ) d = diameter R = Radius θ = Theta Find a. Uc b. d (D, C) c. Let P = B + 3E, UP = d. A x B e. 3B x E f. C x D
23. Given a = 5, b = 4, c = 2, evaluate the following: a) a//c...
23. Given a = 5, b = 4, c = 2, evaluate the following: a) a//c b) a % b c) b **c d) b *= c 27. Given the following var_1 = 2.0 var_2 = "apple" var_3 = 'orange' var_4 = 4 Predict the output of the following statements or indicate that there would be an error. a) print (var_1) b) print (var_2) c) print ("var_3") d) print (var_1 / var_4) e) print (var_4 + var_3) f) print (var_2...
Find the value of a : b : c : d, if a : b = 2 : 3, b : c = 4 : 5 and c : d = 6 : 7.
Find the value of a : b : c : d, if a : b = 2 : 3, b : c = 4 : 5 and c : d = 6 : 7.
Consider the following set of numbers: {3, 5, 2, 5, 5, 15, 2, 2, 4, 4,...
Consider the following set of numbers: {3, 5, 2, 5, 5, 15, 2, 2, 4, 4, 20, 4998, 4} 14. The Q3 of this set is: a. 4 b. 5 c. 2 d. 10 15. The Q1 of this set is: a. 4 b. 5 c. 2 d. 2.5 e. 3
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F 5 B,C 12000 G 3 D,E 7000 H 12 D,E 42000 I 10 F,G 36000 Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made. a) Find the net present value of the project at...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E C 6 9 24 F E 1 7 13 G C 4 10 28 H D,F 2 5 14 I G,F 5 8 17 J H,I 2 5 8 Determine the expected completion time for each activity. Construct the AON network for the activities of this contract and determine the critical path for the project.
4. The duration, in hours, of the effect of the standard dose of a certain drug...
4. The duration, in hours, of the effect of the standard dose of a certain drug on a healthy adult female is thought to be exponentially distributed. The table below shows the results for a random sample of 200 healthy females all given standard dose. Duration 0- 3- 6- 9- 12- 18- 24-36 Females 40 31 31 22 23 22 31 Test the hypothesis that the duration of the effect is exponentially distributed.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT