Question

In: Operations Management

1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity...

1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A, B, and C are week 5, week 7, and week 4, what are the EST and EFT for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input EST in the first blank and EFT in the second blank.)

2)In a project, activity A, B, and C are the successors of activity D. The LSTs of activities A, B, and C are week 10, week 7, and week 9, what are the LST and LFT for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input LST in the first blank and LFT in the second blank.)

Solutions

Expert Solution

1. For calculating EST (Early Start time) and EFT (Early Finish time), we must look at forward path.

Predecessors of D are A, B, C.

EFT of activity A = 5 week

EFT of activity B = 7 week

EFT of activity C = 4 week

EST of an activity = Maximum EFT of its predecessor activities

Therefore,

# EST of activity D = 7 weeks

Given that duration of activity D = 6 week

EFT of activity D = Duration + EST of activity D

EFT of activity D = 6 + 7

# EFT of activity D = 13 weeks

2. For calculating LST (Late Start time) and LFT (Late Finish time), we must look at backward path.

Successors of D are A, B, C.

LST of activity A = 10 week

LST of activity B = 7 week

LST of activity C = 9 week

LFT of an activity = Minimum LST of its successor activities

Therefore,

# LFT of activity D = 7 weeks

Given that duration of activity D = 6 week

LST of activity D = LFT of activity D - Duration

LST of activity D = 7 - 6

# LST of activity D = 1 weeks


Related Solutions

Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2 G D&E 1 H G 4 I F 7 J H&I 2 K J 4 L F 6 Activity Code Early Start Early Finish Late start Later Finish Total Float A 0 3 0 3 0 B 3 6 3 6 0 C 3 5 5 7 2 D 5 7 8 10 3 E...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors Predecessors: A is none B is none C is B D is A & C E is B F is D, E, G G is B H is F I is G J is I What is slack time (float) for A6 weeks---B6 weeks---C5 weeks D4 weeks, E5 weeks F7 weeks, G4 weeks H8 weeks I5 weeks J3 weeks Step 1: Construct a network...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
What activity and it's predecessors would be considered the critical path in the construction schedule of...
What activity and it's predecessors would be considered the critical path in the construction schedule of a two level 14, 000 seat Sports stadium?
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
Laboratory activity 1) 3 testubes A , B and C with 4ml of starch solution 2)...
Laboratory activity 1) 3 testubes A , B and C with 4ml of starch solution 2) 3, A-1, A-2 and A-3 testubes with alfa amylase: testube A-1 is placed in a cold bath, and B-1 in a 37C water bath and C-1 in a boiling bath for 5 min 3) Transfer contents of tube A into ice bath and pour contents of A-1 to tube A, Mix and place tube A back in ice bath. After 10 min add 2...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT