In: Operations Management
1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A, B, and C are week 5, week 7, and week 4, what are the EST and EFT for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input EST in the first blank and EFT in the second blank.)
2)In a project, activity A, B, and C are the successors of activity D. The LSTs of activities A, B, and C are week 10, week 7, and week 9, what are the LST and LFT for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input LST in the first blank and LFT in the second blank.)
1. For calculating EST (Early Start time) and EFT (Early Finish time), we must look at forward path.
Predecessors of D are A, B, C.
EFT of activity A = 5 week
EFT of activity B = 7 week
EFT of activity C = 4 week
EST of an activity = Maximum EFT of its predecessor activities
Therefore,
# EST of activity D = 7 weeks
Given that duration of activity D = 6 week
EFT of activity D = Duration + EST of activity D
EFT of activity D = 6 + 7
# EFT of activity D = 13 weeks
2. For calculating LST (Late Start time) and LFT (Late Finish time), we must look at backward path.
Successors of D are A, B, C.
LST of activity A = 10 week
LST of activity B = 7 week
LST of activity C = 9 week
LFT of an activity = Minimum LST of its successor activities
Therefore,
# LFT of activity D = 7 weeks
Given that duration of activity D = 6 week
LST of activity D = LFT of activity D - Duration
LST of activity D = 7 - 6
# LST of activity D = 1 weeks