The following data were obtained from a project to build a pressure vessel:
Activity Duration Predecessors
Predecessors:
A is none
B is none
C is B
D is A & C
E is B
F is D, E, G
G is B
H is F
I is G
J is I
What is slack time (float) for
A6 weeks---B6 weeks---C5 weeks D4 weeks, E5 weeks F7 weeks, G4 weeks H8 weeks I5 weeks J3 weeks
Step 1: Construct a network diagram for the project.
Calculate completion time
Identity critical path
What is slack time (float) for A?
What is slack time (float) for D?
What is slack time (float) for E?
What is slack time (float) for G?
Based on the given data, we prepare a network diagram as shown below:
The above network diagram in form of formulas is shown below for better understanding and reference:
The above project diagram is prepared as per legend shown in top-left corner.
EST = Early start time
LST = Late start time
EFT = Early finish time
LFT = Late finish time
SLK = Slack = LST - EST or Slack = LFT - EFT
The EST of an activity = EFT of previous activity
EFT of an activity = EST + Duration
Similarly LFT & LST are calculated during backward pass. The activity END is only a dummy activity which is introduced for backward pass calculations only. It will not be considered for any other purpose.
There are multiple paths in the diagram. However, path B-C-D-F-H is the critical path.
As seen from the network diagram, the project completion time = 30 weeks
As seen from the network diagram and the legend,
Slack time for A = 5 weeks
Slack time for D = 0 weeks
Slack time for E = 4 weeks
Slack time for G = 5 weeks
-----------------------------------------------------------------------------------------------------------------------