Question

In: Operations Management

The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors...

The following data were obtained from a project to build a pressure vessel:

Activity Duration Predecessors

Predecessors:

A is none

B is none

C is B

D is A & C

E is B

F is D, E, G

G is B

H is F

I is G

J is I

What is slack time (float) for

A6 weeks---B6 weeks---C5 weeks D4 weeks, E5 weeks F7 weeks, G4 weeks H8 weeks I5 weeks J3 weeks

Step 1: Construct a network diagram for the project.

Calculate completion time

Identity critical path

What is slack time (float) for A?

What is slack time (float) for D?

What is slack time (float) for E?

What is slack time (float) for G?

Solutions

Expert Solution

Based on the given data, we prepare a network diagram as shown below:

The above network diagram in form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per legend shown in top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration

Similarly LFT & LST are calculated during backward pass. The activity END is only a dummy activity which is introduced for backward pass calculations only. It will not be considered for any other purpose.

There are multiple paths in the diagram. However, path B-C-D-F-H is the critical path.

As seen from the network diagram, the project completion time = 30 weeks

As seen from the network diagram and the legend,

Slack time for A = 5 weeks

Slack time for D = 0 weeks

Slack time for E = 4 weeks

Slack time for G = 5 weeks

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.

If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!


Related Solutions

Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity...
1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A, B, and C are week 5, week 7, and week 4, what are the EST and EFT for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input EST in the first blank and EFT in the second blank.) 2)In a project, activity A, B, and C are the successors...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2 G D&E 1 H G 4 I F 7 J H&I 2 K J 4 L F 6 Activity Code Early Start Early Finish Late start Later Finish Total Float A 0 3 0 3 0 B 3 6 3 6 0 C 3 5 5 7 2 D 5 7 8 10 3 E...
The following data were obtained in a study of the relationship between diastolic blood pressure (Y)...
The following data were obtained in a study of the relationship between diastolic blood pressure (Y) and age (X) for boys 5 to 13 years old. X 5 8 11 7 13 12 12 6 Y 63 67 74 64 75 69 90 60 Fit a simple linear regression model to the data and plot the residuals against the fitted values. Omit case 7 and refit the model. Plot the residuals versus the fitted values and compare to what you...
The following sample data were obtained from different second-year medical students who took blood pressure measurements...
The following sample data were obtained from different second-year medical students who took blood pressure measurements of the same person. Conduct a formal hypothesis test to test for a linear correlation between the systolic and diastolic readings. Use a 0.05 significance level. Systolic 138 130 135 140 120 Diastolic 82 91 100 100 80 Does there appear to be a linear correlation between the systolic and diastolic readings? Yes or No?
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
The following data were obtained from a batch experiment for the reaction where A is converted...
The following data were obtained from a batch experiment for the reaction where A is converted to B. 1)Determine the order of the reaction             Time (min)      0           10        20        40        60        80        100             A (mg/lit)        100      74        55        30        17        9          5 2) Consider a first order reaction taking place in a batch reactor. Develop an expression for the detention time in the reactor.
The following data were obtained from the accounting information system of Attawfik Corporation:
The following data were obtained from the accounting information system of Attawfik Corporation:                        Units           Total Cost                                        Month         Produced                                        January              60       SAR1,533.4                     February            50               1,300                        March                80               2,000                        April                  30                  833.5                     a.   Use the data for February and March and the two - point method to determine a cost function. b.   Use the high - low method to determine a cost function. C. How do you think that a cost function may provide poor estimates of future costs?  
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT