Question

In: Accounting

In 2015 The Hi Tower Construction Company, started a 3 year project at a fixed contract...

In 2015 The Hi Tower Construction Company, started a 3 year project at a fixed contract price of $21,000,000. The estimated construction costs were $14,400,000. The project was completed on time during the third year. The following information is available for the three year period of the construction project.

2015    2016       2017

Costs Incurred to Date $6,420,000 $12,322,000 $15,135,000

Estimated Costs to Complete 8,150,000    2,368,000        --

Billings to Date 6,400,000   15,150,000   21,000,000

Collections to Date 5,150,000   15,110,000   20,900,000

Required

1. Compute the amount of gross profit to be recognized for

each of the three years using the percentage of completion.

2. Prepare all necessary journal entries for the 2015, 2016, and 2017 years using the percentage of completion method.

3. Compute gross profit to be recognized for the three years of 2015, 2016, and 2017 using the completed contract method.

4. For each of the three years of 2015, 2016, and 2017:

a. Prepare the Income Statement section to report the percentage of completion information.   

b. Prepare the Balance Sheet section to report the percentage of completion information.

Solutions

Expert Solution

for your referance formula sheet as under


Related Solutions

In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...
In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract price of $22,000,000. The estimated construction costs were $15,500,000. The project was completed on time during the 2917 year. The following information is available for the three year period of the construction project. 2015 2016 2017 Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000 Estimated Costs to Complete 9,282,000 3,090,000 -- Billings to Date 6,400,000 18,890,000 22,000,000 Collections to Date 5,100,000 17,110,000 21,630,000 Required 1....
In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...
In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract price of $22,000,000. The estimated construction costs were $15,500,000. The project was completed on time during the 2917 year. The following information is available for the three year period of the construction project.   2015    2016       2017 Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000 Estimated Costs to Complete 9,282,000    3,090,000        -- Billings to Date 6,400,000   18,890,000   22,000,000 Collections to Date 5,100,000   17,110,000...
During 2015, Nilsen Company started a construction job with a contract price of $3,200,000. The job...
During 2015, Nilsen Company started a construction job with a contract price of $3,200,000. The job was completed in 2017. The following information is available: 2015 2016 2017 Costs incurred to date $ 800,000 $1,650,000 $2,140,000 Estimated costs to complete 1,200,000 550,000 -0- Billings to date 600,000 1,800,000 3,200,000 Collections to date 540,000 1,620,000 2,850,000 Required: a. Prepare all the necessary accounting entries for 2015, 2016 &2017, assuming the percentage-of-completion method is used. b. Prepare all the necessary accounting entries...
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year.
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? a. $0 b. $1,050,000 c....
During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000.   The job...
During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000.   The job was completed in 2017. The following information is available: 2015 2016 2017 Costs incurred to date 500,000 900,000 1,100,000 Estimated costs to complete 600,000 200,000 0 Billings to date 500,000 1,400,000 2,000,000 Collections to date 450,000 1,300,000 1,800,000 Instructions: (a) Compute the amount of gross profit to be recognized each year assuming the percentage of       completion method is used. (b) ****EXTRA CREDIT -...
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT