Question

In: Accounting

Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below:

                                                                                    2012                           2013

Costs incurred during the year                               $450,000                $ 1.100,000

Estimated costs to complete 1,050,000                      0

Billings during the year                                            400,000                    1,400,000

Cash collections during the year                             300,000                     1,500,000

Assume that Beavis uses the percentage- of- completion method for revenue recognition.

Required:

Compute the amount of gross profit recognized during 2012 and 2013.

Prepare all journal entries related to the construction project in 2012 and 2013.

Prepare Statement of Financial Position end of 2012 and 2013 (if any).

(please provide the answer step by step)

Solutions

Expert Solution

2012:

$1800000

Contract price

450000

Actual costs to date

1050000

Estimated costs to complete

1500000

Total estimated project costs

Estimated total gross profit

300000

Percentage of completion: $450,000/ $1,500,000

30%

Gross profit recognized

$90000

2013:

Contract price

$1800000

Costs incurred:

2012

$450000

2013

1100000

Total cost

1550000

Total gross profit

250000

Recognized in 2012

90000

Recognized in 2013

$160000

General journal

Debit

Credit

2012:

Construction in progress

450000

Cash

450000

Accounts receivable

400000

Billings on construction contract

400000

Cash

300000

Accounts receivable

300000

Construction in progress

90000

Cost of construction

450000

Revenue from long-term contracts

540000

2013:

Construction in progress

1100000

Cash

1100000

Accounts receivable

1400000

Billings on construction contract

1400000

Cash

1500000

Accounts receivable

1500000

Construction in progress

160000

Cost of construction

1100000

Revenue from long-term contracts

1260000

Billings on construction contract

1800000

Construction in progress

1800000

2012:

$0

2013:

Contract price

$1800000

Costs incurred:

2012:

$450000

2013:

$1100000

Total costs

$1550000

Total gross profit

$250000


Related Solutions

Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 486500 $1,000,000 Estimated costs to complete 903,500 0 Billings during the year 455,000 1,245,000 Cash collections during the year 355,000 1,345,000 ) Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,820,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 518,000 $ 1,120,000 Estimated costs to complete 962,000 0 Billings during the year 410,000 1,410,000 Cash collections during the year 310,000 1,510,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,900,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 420,000 $ 1,200,000 Estimated costs to complete 980,000 0 Billings during the year 450,000 1,450,000 Cash collections during the year 350,000 1,550,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016   Costs incurred during the year $ 399,000 $1,060,000      Estimated costs to complete 931,000 0      Billings during the year 485,000 1,330,000      Cash collections during the year 385,000 1,430,000    Required information Assume that Beavis recognizes revenue on this contract over time...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,720,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $ 411,000 $1,020,000 Estimated costs to complete 959,000 0 Billings during the year 465,000 1,310,000 Cash collections during the year 365,000 1,410,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required:...
1. Beavis Construction Company was the low bidder on a construction project to build an earthen...
1. Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                           2017                           2018 Costs incurred during the year                    $ 450,000                  $1,100,000 Estimated costs to complete                       1,050,000                                  0 Billings during the year                                 400,000                    1,400,000 Cash collections during the year                    300,000                    1,500,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...