In: Accounting
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below:
2012 2013
Costs incurred during the year $450,000 $ 1.100,000
Estimated costs to complete 1,050,000 0
Billings during the year 400,000 1,400,000
Cash collections during the year 300,000 1,500,000
Assume that Beavis uses the percentage- of- completion method for revenue recognition.
Required:
Compute the amount of gross profit recognized during 2012 and 2013.
Prepare all journal entries related to the construction project in 2012 and 2013.
Prepare Statement of Financial Position end of 2012 and 2013 (if any).
(please provide the answer step by step)
2012: |
$1800000 |
|
Contract price |
450000 |
|
Actual costs to date |
1050000 |
|
Estimated costs to complete |
1500000 |
|
Total estimated project costs |
||
Estimated total gross profit |
300000 |
|
Percentage of completion: $450,000/ $1,500,000 |
30% |
|
Gross profit recognized |
$90000 |
|
2013: |
||
Contract price |
$1800000 |
|
Costs incurred: |
||
2012 |
$450000 |
|
2013 |
1100000 |
|
Total cost |
1550000 |
|
Total gross profit |
250000 |
|
Recognized in 2012 |
90000 |
|
Recognized in 2013 |
$160000 |
General journal |
Debit |
Credit |
2012: |
||
Construction in progress |
450000 |
|
Cash |
450000 |
|
Accounts receivable |
400000 |
|
Billings on construction contract |
400000 |
|
Cash |
300000 |
|
Accounts receivable |
300000 |
|
Construction in progress |
90000 |
|
Cost of construction |
450000 |
|
Revenue from long-term contracts |
540000 |
|
2013: |
||
Construction in progress |
1100000 |
|
Cash |
1100000 |
|
Accounts receivable |
1400000 |
|
Billings on construction contract |
1400000 |
|
Cash |
1500000 |
|
Accounts receivable |
1500000 |
|
Construction in progress |
160000 |
|
Cost of construction |
1100000 |
|
Revenue from long-term contracts |
1260000 |
|
Billings on construction contract |
1800000 |
|
Construction in progress |
1800000 |
2012: |
$0 |
|
2013: |
||
Contract price |
$1800000 |
|
Costs incurred: |
||
2012: |
$450000 |
|
2013: |
$1100000 |
|
Total costs |
$1550000 |
|
Total gross profit |
$250000 |