Question

In: Accounting

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000....

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year.

Solutions

Expert Solution

Formula sheet

A B C D E F G H I J
2 1)
3 Contract Value 10000000
4 Revenue recognized over the years can be calculated using percentage completion method.
5 Revenue recognized in a year= (% of project completed during the year*Total Contract Value) - Revenue recognized till previous years
6 % of project completed in a year = Cumulative Expenditure incurred till the year / Total estimated cost of contract.
7
8 Revenue recognized upon completion is the total contract value.
9
10 Gross profit in a period = Revenue recognized - Cost incurred in the year
11
12 Cost incurred during the year Cumulative cost Estimated cost to complete
13 Situation Year1 Year1 Year1
14 1 3000000 =D14 5000000
15
16
17 For Situation 1 revenue recognized over the years can be calculated as follows:
18
19 Situation Year1
20 Contract Price =$D$3
21 Less:
22 Cost incurred to date =E14
23 Estimated Further Cost =F14
24 Estimated total cost =D22+D23
25
26 Percentage of completion = Cost incurred to date / Estimated total cost =D22/D24 =D22/D24
27
28 Revenue Recognized =D20*D26
29 Cost incurred during the year =D14
30 Gross Profit =D28-D29
31
32
33
34 Given the following data: Year1
35 Cost incurred during the year =D14
36 Estimated cost to complete as of year end =F14
37 Billings during the year 4000000
38 Cash Collections during the year 3500000
39 Revenue recognized =D28
40 Gross Profit =D30
41
42 Journal Entries will be as follows:
43
44 1)
45 Record Cost Incurred
46 Account Debit Credit
47 Construction in progress =E48
48 Cash =D35
49
50 2)
51 Record Billing on Contract
52 Account Debit Credit
53 Account Receivables =E54
54 Billings on construction contract =D37
55
56 3)
57 Record Payment Received
58 Account Debit Credit
59 Cash =D38
60 Account Receivables =D59
61
62 4)
63 Record revenue/cost during construction period
64 Account Debit Credit
65 construction in progress =E67-D66
66 construction Expense =D35
67 construction Revenue =D39
68
69
70 Balance Sheet:
71
72 Account Receivables = Billings - Cash Collection
73 Construction in process = Cost incurred + Gross Profit
74 If construction in progress is in excess of Billings then cost and profit in excess of billings is an asset
75 whereas if the construction in progress is in smaller than billings then billings in excess of cost and profit is an liability.
76
77
78 Balance sheet will be as follows:
79 Current Assets Year1
80 Account Receivables =D37-D38
81 Consruction in progress =D35+D40
82 Less:Billings =D37
83 Cost and profit in excess of billings =MAX(D81-D82,0)
84 Current Liabilities
85 Billings in excess of cost and profit =MAX(D82-D81,0)
86

Related Solutions

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? a. $0 b. $1,050,000 c....
The Young Company enters into a long-term project to build a new office building. The Contract...
The Young Company enters into a long-term project to build a new office building. The Contract price is $9,000,000 and Young expects to complete the project in three years. Young gives you the following information for the first two years regarding the project: 2017 2018 Actual costs incurred during year 2,400,000 3,800,000 Estimated costs to complete at as of December 31: 5,100,000 3,000,000 Amounts billed to customer 2,800,000 4,100,000 Collections from customer 2,600,000 3,400,000 Required: 1.    Prepare the journal entries...
A construction company entered into a fixed-price contract to build an office building for $28 million....
A construction company entered into a fixed-price contract to build an office building for $28 million. Construction costs incurred during the first year were $8 million and estimated costs to complete at the end of the year were $12 million. During the first year the company billed its customer $10 million, of which $4 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
A construction company entered into a fixed-price contract to build an office building for $38 million....
A construction company entered into a fixed-price contract to build an office building for $38 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $18 million. During the first year the company billed its customer $14 million, of which $7 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 50 $ 150 $ 45 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018   Costs incurred during the year $ 50 Estimated costs to complete as of December 31 $200 2019  Costs incurred during...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 40 $ 80 $ 50 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 70 $ 60 $ 30 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $340 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 40 $ 120 $ 50 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 70 $ 60 $ 30 Estimated costs to complete as of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT