In: Accounting
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year.
Formula sheet
A | B | C | D | E | F | G | H | I | J |
2 | 1) | ||||||||
3 | Contract Value | 10000000 | |||||||
4 | Revenue recognized over the years can be calculated using percentage completion method. | ||||||||
5 | Revenue recognized in a year= (% of project completed during the year*Total Contract Value) - Revenue recognized till previous years | ||||||||
6 | % of project completed in a year = Cumulative Expenditure incurred till the year / Total estimated cost of contract. | ||||||||
7 | |||||||||
8 | Revenue recognized upon completion is the total contract value. | ||||||||
9 | |||||||||
10 | Gross profit in a period = Revenue recognized - Cost incurred in the year | ||||||||
11 | |||||||||
12 | Cost incurred during the year | Cumulative cost | Estimated cost to complete | ||||||
13 | Situation | Year1 | Year1 | Year1 | |||||
14 | 1 | 3000000 | =D14 | 5000000 | |||||
15 | |||||||||
16 | |||||||||
17 | For Situation 1 revenue recognized over the years can be calculated as follows: | ||||||||
18 | |||||||||
19 | Situation | Year1 | |||||||
20 | Contract Price | =$D$3 | |||||||
21 | Less: | ||||||||
22 | Cost incurred to date | =E14 | |||||||
23 | Estimated Further Cost | =F14 | |||||||
24 | Estimated total cost | =D22+D23 | |||||||
25 | |||||||||
26 | Percentage of completion = Cost incurred to date / Estimated total cost | =D22/D24 | =D22/D24 | ||||||
27 | |||||||||
28 | Revenue Recognized | =D20*D26 | |||||||
29 | Cost incurred during the year | =D14 | |||||||
30 | Gross Profit | =D28-D29 | |||||||
31 | |||||||||
32 | |||||||||
33 | |||||||||
34 | Given the following data: | Year1 | |||||||
35 | Cost incurred during the year | =D14 | |||||||
36 | Estimated cost to complete as of year end | =F14 | |||||||
37 | Billings during the year | 4000000 | |||||||
38 | Cash Collections during the year | 3500000 | |||||||
39 | Revenue recognized | =D28 | |||||||
40 | Gross Profit | =D30 | |||||||
41 | |||||||||
42 | Journal Entries will be as follows: | ||||||||
43 | |||||||||
44 | 1) | ||||||||
45 | Record Cost Incurred | ||||||||
46 | Account | Debit | Credit | ||||||
47 | Construction in progress | =E48 | |||||||
48 | Cash | =D35 | |||||||
49 | |||||||||
50 | 2) | ||||||||
51 | Record Billing on Contract | ||||||||
52 | Account | Debit | Credit | ||||||
53 | Account Receivables | =E54 | |||||||
54 | Billings on construction contract | =D37 | |||||||
55 | |||||||||
56 | 3) | ||||||||
57 | Record Payment Received | ||||||||
58 | Account | Debit | Credit | ||||||
59 | Cash | =D38 | |||||||
60 | Account Receivables | =D59 | |||||||
61 | |||||||||
62 | 4) | ||||||||
63 | Record revenue/cost during construction period | ||||||||
64 | Account | Debit | Credit | ||||||
65 | construction in progress | =E67-D66 | |||||||
66 | construction Expense | =D35 | |||||||
67 | construction Revenue | =D39 | |||||||
68 | |||||||||
69 | |||||||||
70 | Balance Sheet: | ||||||||
71 | |||||||||
72 | Account Receivables = Billings - Cash Collection | ||||||||
73 | Construction in process = Cost incurred + Gross Profit | ||||||||
74 | If construction in progress is in excess of Billings then cost and profit in excess of billings is an asset | ||||||||
75 | whereas if the construction in progress is in smaller than billings then billings in excess of cost and profit is an liability. | ||||||||
76 | |||||||||
77 | |||||||||
78 | Balance sheet will be as follows: | ||||||||
79 | Current Assets | Year1 | |||||||
80 | Account Receivables | =D37-D38 | |||||||
81 | Consruction in progress | =D35+D40 | |||||||
82 | Less:Billings | =D37 | |||||||
83 | Cost and profit in excess of billings | =MAX(D81-D82,0) | |||||||
84 | Current Liabilities | ||||||||
85 | Billings in excess of cost and profit | =MAX(D82-D81,0) | |||||||
86 |