Question

In: Accounting

During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000.   The job...

During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000.  
The job was completed in 2017. The following information is available:
2015 2016 2017
Costs incurred to date 500,000 900,000 1,100,000
Estimated costs to complete 600,000 200,000 0
Billings to date 500,000 1,400,000 2,000,000
Collections to date 450,000 1,300,000 1,800,000
Instructions:
(a) Compute the amount of gross profit to be recognized each year assuming the percentage of
      completion method is used.
(b) ****EXTRA CREDIT - Prepare all necessary journal entries for 2016.
2015 2016 2017
2,000,000 2,000,000 2,000,000

Solutions

Expert Solution

Please give positive ratings so I can keep answering. Thanks!

Calculation of Gross Profit Journal Entries
Particulars 2015 2016 2017 Journal Entries 2015 2016 2017
Contract Price          2,000,000          2,000,000          2,000,000 A Costs Incurred CIP (Work-in-progress) Dr.       500,000      400,000        200,000
Cost Incurred to date             500,000             900,000          1,100,000 B Cash Cr.       500,000      400,000        200,000
Estimated cost to complete             600,000             200,000                        -   C
Estimated total cost          1,100,000          1,100,000          1,100,000 D=B+C Billing Accounts Receivable Dr.       500,000      900,000     1,100,000
Percentage complete 45.45% 81.82% 100.00% E=B/D Billing on CIP Cr.       500,000      900,000     1,100,000
(Cost Incurred to date/Estimated total cost)
Cost Incurred during the year       500,000.00       400,000.00       200,000.00 F Receiving Payments Cash Dr.       450,000      850,000        500,000
Cost Incurred to date of current year less Cost Incurred to date of previous year Accounts Receivable Cr.       450,000      850,000        500,000
Revenue to be recognized             909,091             727,273             363,636 G=A*E
(Contract Price*Percentage complete)- revenue previously recognized Period end adjustments for Revenue Construction Expense Dr.       500,000      400,000        200,000
Year 2015: 45.45% completed. Revenue recognized = 45.45% x $2,000,000 = $909,091. CIP (Work-in-progress) Dr.       409,091      327,273        163,636
Year 2016: 81.82% completed. Revenue recognized = 81.82% x $2,000,000 – $909,091 (previously recognized) = $727,273. Construction Revenue Cr.       909,091      727,273        363,636
Year 2017: 100% completed. Revenue recognized = 100% x $2,000,000 – $909,091– $727,273 (previously recognized) = $363,636.
Gross Profit/(Loss)       409,090.91       327,272.73       163,636.36 H=G-F Completion of Project Billing on CIP Dr.     2,000,000
Billings to Date       500,000.00    1,400,000.00    2,000,000.00 CIP (Work-in-progress) Cr.     2,000,000
Billings during the year       500,000.00       900,000.00    1,100,000.00
Billings to Date of current year less Billings to Date of previous year
Collections to Date       450,000.00    1,300,000.00    1,800,000.00
Collection during the year       450,000.00       850,000.00       500,000.00
Collections to Date of current year less Collections to Date of previous year

Related Solutions

During 2015, Nilsen Company started a construction job with a contract price of $3,200,000. The job...
During 2015, Nilsen Company started a construction job with a contract price of $3,200,000. The job was completed in 2017. The following information is available: 2015 2016 2017 Costs incurred to date $ 800,000 $1,650,000 $2,140,000 Estimated costs to complete 1,200,000 550,000 -0- Billings to date 600,000 1,800,000 3,200,000 Collections to date 540,000 1,620,000 2,850,000 Required: a. Prepare all the necessary accounting entries for 2015, 2016 &2017, assuming the percentage-of-completion method is used. b. Prepare all the necessary accounting entries...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date       $393,900       $760,380       $1,059,000 Estimated costs to complete       616,100       341,620       –0– Billings to date       299,000       905,000       1,610,000 Collections to date       268,000       818,000       1,421,000    Compute the amount of gross profit to be recognized each year, assuming the...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $885,330 $1,060,000 Estimated costs to complete 585,800 207,670 –0– Billings to date 299,000 908,000 1,590,000 Collections to date 273,000 819,000 1,435,000 Part 1 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT