Question

In: Accounting

Bohr Co is a construction company and has entered into a contract with a fixed price...

Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value.

The following information relates to the contract:

£

Costs incurred to date

360,000

Estimate of the costs to complete the contract

125,000

Value of work certified by independent architect

450,000

Amounts invoiced to client

250,000

Requirement

  1. Prepare the relevant Statement of profit or loss and Statement of financial position extracts in respect of the above contract for the year ended 30thNovember 20X8.       

  1. Before the financial statements are finalised, technical problems on the contract mean that costs to complete are reassessed to £275,000. Prepare the amended Statement of profit or loss extract for the year ended 30thNovember 20X8. A Statement of financial position is notrequired.                                                                                                    

  1. Explain the different approaches in a) and b).

Solutions

Expert Solution

Solution a

Percentage completion = Work Certified / Contract Value * 100 = 450000/ 600000*100=75 %

Proportionate costs = Total Cost * Percentage completion = (360000+125000)*75% = 363750

Statement of profit or loss

Particulars Amount Particulars Amount
Project cost incurred 360000 Project Revenue 450000
Project cost yet to incurr 3750
Profit 86250
450000 450000

Statement of Financial Position

Particular Amount Particulars Amount
Capital (Profit) 86250 Debtor
Due to customer 363750 - Billed 250000
- Unbilled 200000
Total 450000 Total 450000

Solution b

Percentage completion = Work Certified / Contract Value * 100 = 450000/ 600000*100=75 %

Total Cost = 360000+275000 = 635000

Contract price = 600000

Total Forseeable loss to be recognised as expense = 635000 - 600000 = 35000

Proportionate costs = Total Cost * Percentage completion = (360000+275000-35000#)*75% = 363750

# excluding loss recognised immediately

Statement of profit or loss

Particulars Amount Particulars Amount
Project cost incurred 360000 Project Revenue 450000
Project cost yet to incurr 90000
Forseeable loss 35000 Loss 35000
485000 485000

Solution c

Approach in solution a: Proportionate project costs are recorded

Approach in solution b: Since project cost is exceeding project revenue, the forseeable loss is recognised immediately as expense. And the remaining project cost is apportioned proportionately based on percentage completion.


Related Solutions

A construction company entered into a fixed-price contract to build an office building for $28 million....
A construction company entered into a fixed-price contract to build an office building for $28 million. Construction costs incurred during the first year were $8 million and estimated costs to complete at the end of the year were $12 million. During the first year the company billed its customer $10 million, of which $4 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
A construction company entered into a fixed-price contract to build an office building for $38 million....
A construction company entered into a fixed-price contract to build an office building for $38 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $18 million. During the first year the company billed its customer $14 million, of which $7 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,020,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,020,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,660,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT