In: Accounting
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8. Bohr Co measures percentage completion using the work certified as a proportion of contract value.
The following information relates to the contract:
£ |
|
Costs incurred to date |
360,000 |
Estimate of the costs to complete the contract |
125,000 |
Value of work certified by independent architect |
450,000 |
Amounts invoiced to client |
250,000 |
Requirement
Solution a
Percentage completion = Work Certified / Contract Value * 100 = 450000/ 600000*100=75 %
Proportionate costs = Total Cost * Percentage completion = (360000+125000)*75% = 363750
Statement of profit or loss
Particulars | Amount | Particulars | Amount |
Project cost incurred | 360000 | Project Revenue | 450000 |
Project cost yet to incurr | 3750 | ||
Profit | 86250 | ||
450000 | 450000 |
Statement of Financial Position
Particular | Amount | Particulars | Amount |
Capital (Profit) | 86250 | Debtor | |
Due to customer | 363750 | - Billed | 250000 |
- Unbilled | 200000 | ||
Total | 450000 | Total | 450000 |
Solution b
Percentage completion = Work Certified / Contract Value * 100 = 450000/ 600000*100=75 %
Total Cost = 360000+275000 = 635000
Contract price = 600000
Total Forseeable loss to be recognised as expense = 635000 - 600000 = 35000
Proportionate costs = Total Cost * Percentage completion = (360000+275000-35000#)*75% = 363750
# excluding loss recognised immediately
Statement of profit or loss
Particulars | Amount | Particulars | Amount |
Project cost incurred | 360000 | Project Revenue | 450000 |
Project cost yet to incurr | 90000 | ||
Forseeable loss | 35000 | Loss | 35000 |
485000 | 485000 |
Solution c
Approach in solution a: Proportionate project costs are recorded
Approach in solution b: Since project cost is exceeding project revenue, the forseeable loss is recognised immediately as expense. And the remaining project cost is apportioned proportionately based on percentage completion.