In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract price of $22,000,000. The estimated construction costs were $15,500,000. The project was completed on time during the 2917 year. The following information is available for the three year period of the construction project.
2015 2016 2017
Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000
Estimated Costs to Complete 9,282,000 3,090,000 --
Billings to Date 6,400,000 18,890,000 22,000,000
Collections to Date 5,100,000 17,110,000 21,630,000
For each of the three years of 2015, 2016, and 2017:
a. Prepare the Income Statement section for Big Boss Construction reporting percentage of completion information.
b. Prepare the Balance Sheet section for Big Boss Constriction reporting percentage of completion information.
Answer | |||
a) INCOME STATEMENT SECTION | |||
Particulars | Year 2015(fig in$) | Year 2016(fig in$) | Year 2017(fig in$) |
Sales | 88,00,000 | 1,76,00,000 | 2,20,00,000 |
Less : Cost of goods sold | 61,88,000 | 1,23,60,000 | 1,58,75,000 |
Gross profit | 26,12,000 | 52,40,000 | 61,25,000 |
b. BALANCE SHEET": | |||
Current liabilities | |||
CIP | |||
lESS: bILLINGS ON |