Question

In: Accounting

During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job...

During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized in 2018 $ Gross profit recognized in 2019 $

Solutions

Expert Solution

Ref Particulars 2017 2018 2019
a Cost incurred during the year $             405,900 $             360,600 $             309,500
A Cumulative costs incurred till date $             405,900 $             766,500 $         1,076,000
b Estimated costs to complete as of year end $             584,100 $             328,500 $                        -  
B= A+b Total cost of completing the contract $             990,000 $         1,095,000 $         1,076,000
Ref Particulars 2017 2018 2019
C=A/B Percentage completion 41.00% 70.00% 100.00%
D Contract amount $         1,610,000 $         1,610,000 $         1,610,000
E=C*D Revenue earned till date $             660,100 $         1,127,000 $         1,610,000
F Revenue already recognised $                        -   $             660,100 $         1,127,000
G=E-F Revenue for the year $             660,100 $             466,900 $             483,000
H= G-a Gross profit $             254,200 $             106,300 $             173,500

Related Solutions

During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date       $393,900       $760,380       $1,059,000 Estimated costs to complete       616,100       341,620       –0– Billings to date       299,000       905,000       1,610,000 Collections to date       268,000       818,000       1,421,000    Compute the amount of gross profit to be recognized each year, assuming the...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Prepare all necessary journal entries for 2021. (Credit account...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 (a) Your answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
During 2020, Flint Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Flint Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...
During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $366,300 $831,440 $1,067,000 Estimated costs to complete 623,700 262,560 –0– Billings to date 297,000 894,000 1,590,000 Collections to date 270,000 816,000 1,417,000 a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit in 2017 Gross profit in 2018...
During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job...
During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $404,000 $853,160 $1,073,000 Estimated costs to complete 606,000 254,840 –0– Billings to date 301,000 904,000 1,580,000 Collections to date 271,000 812,000 1,418,000 Instructions: Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT