Question

In: Accounting

In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...

In 2015 The Big Boss Construction Company, started a 3 year
project at a fixed contract price of $22,000,000. The estimated
construction costs were $15,500,000. The project was completed
on time during the 2917 year. The following information is
available for the three year period of the construction project.
2015 2016 2017
Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000
Estimated Costs to Complete 9,282,000 3,090,000 --
Billings to Date 6,400,000 18,890,000 22,000,000
Collections to Date 5,100,000 17,110,000 21,630,000
Required
1. Compute the amount of gross profit to be recognized for
each of the three years using the percentage of completion.
2. Prepare all necessary journal entries for the 2015, 2016, and
2017 years using the percentage of completion method.
3. Compute gross profit to be recognized for the three years of
2015, 2016, and 2017 using the completed contract method.
4. For each of the three years of 2015, 2016, and 2017:
a. Prepare the Income Statement section for Big Boss Construction
reporting percentage of completion information.   
b. Prepare the Balance Sheet section for Big Boss Constriction
reporting percentage of completion information.

Solutions

Expert Solution

  1. Recognition of Gross Profit under the Percentage of completion method

Particulars

       Year 2015(FIG IN $)

     Year 2016(FIG IN $)

      Year 2017(FIG IN $)

Contract Price

22000000

22000000

22000000

Cost incurred

To date

6188000

12360000

15875000

Add:estimated

Cost to complete

9282000

15470000

3090000

15450000

-

15875000

Total Estimated

Profit

6530,000

65,50,000

61,25,000

Percentage completed

Till date

40%

80%

100%

Total Gross Profit

Recognized

26,12,000

52,40,000

61,25,000

2.

Journal entries under percentage of completion method

Particulars

Debit($)

Credit( $)

Debit($)

Credit($)

Debit($)

Credit($)

Cost incurred to

Date

Construction in

Progress(CIP)

6188000

12360000

15875000

Accounts payable

6188000

12360000

15875000

Billing to date

Accounts Receivable

6400000

18890000

22000000

   Billing on CIP

6400000

18890000

22000000

Receiving Payament

Cash

5100000

17110000

21630000

   Accounts Receivable

5100000

17110000

21630000

Recording Revenue

Billing on CIP

6400000

18890000

22000000

Construction revenue a/c

6400000

18890000

22000000

Recording Expenses

Cost of construction

6188000

12360000

15875000

Construction in progress(CIP)

        

6188000

12360000

15875000

3.Recognition of Gross Profit under the completion contract method

Particulars

       Year 2015(fig in$)

     Year 2016(fig in $)

      Year 2017(fig in $)

Contract Price

22000000

22000000

22000000

Cost incurred

To date

6188000

12360000

15875000

Add:estimated

Cost to complete

9282000

15470000

3090000

15450000

-

15875000

Total Estimated

Profit

6530,000

65,50,000

61,25,000

Percentage completed

Till date

40%

80%

100%

Total Gross Profit

Recognized

Not applicable

Not applicable

61,25,000

4. a) INCOME STATEMENT SECTION

Particulars

Year 2015(fig in$)

Year 2016(fig in$)

Year 2017(fig in$)

Sales

8800000

17600000

22000000

Less : Cost of goods sold

6188000

12360000

15875000

Gross profit

2612000

5240,000

61,25,000

b. BALANCE SHEET":

Current liabilities

CIP

lESS: bILLINGS ON

construction


Related Solutions

In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...
In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract price of $22,000,000. The estimated construction costs were $15,500,000. The project was completed on time during the 2917 year. The following information is available for the three year period of the construction project.   2015    2016       2017 Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000 Estimated Costs to Complete 9,282,000    3,090,000        -- Billings to Date 6,400,000   18,890,000   22,000,000 Collections to Date 5,100,000   17,110,000...
In 2015 The Hi Tower Construction Company, started a 3 year project at a fixed contract...
In 2015 The Hi Tower Construction Company, started a 3 year project at a fixed contract price of $21,000,000. The estimated construction costs were $14,400,000. The project was completed on time during the third year. The following information is available for the three year period of the construction project. 2015    2016       2017 Costs Incurred to Date $6,420,000 $12,322,000 $15,135,000 Estimated Costs to Complete 8,150,000    2,368,000        -- Billings to Date 6,400,000   15,150,000   21,000,000 Collections to Date 5,150,000   15,110,000...
During 2015, Nilsen Company started a construction job with a contract price of $3,200,000. The job...
During 2015, Nilsen Company started a construction job with a contract price of $3,200,000. The job was completed in 2017. The following information is available: 2015 2016 2017 Costs incurred to date $ 800,000 $1,650,000 $2,140,000 Estimated costs to complete 1,200,000 550,000 -0- Billings to date 600,000 1,800,000 3,200,000 Collections to date 540,000 1,620,000 2,850,000 Required: a. Prepare all the necessary accounting entries for 2015, 2016 &2017, assuming the percentage-of-completion method is used. b. Prepare all the necessary accounting entries...
During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000.   The job...
During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000.   The job was completed in 2017. The following information is available: 2015 2016 2017 Costs incurred to date 500,000 900,000 1,100,000 Estimated costs to complete 600,000 200,000 0 Billings to date 500,000 1,400,000 2,000,000 Collections to date 450,000 1,300,000 1,800,000 Instructions: (a) Compute the amount of gross profit to be recognized each year assuming the percentage of       completion method is used. (b) ****EXTRA CREDIT -...
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
Big Construction Company signs a contract on 1 July 2019, agreeing to build a warehouse for...
Big Construction Company signs a contract on 1 July 2019, agreeing to build a warehouse for Buyer Corporation Ltd at a fixed contract price of $10 million. Buyer Ltd will be in control of the asset throughout the construction process. Big Construction Company estimates that construction costs will be as follows: 2019 2.5 million 2020 $4 million 2021 $1.5 million The contract provides that Buyer Corporation Ltd will make payments on 31 December each year as follows: 2019 $2 million...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT