Question

In: Accounting

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method?

a. $0
b. $1,050,000

c. $2,650,000

d. $4,250,000

Solutions

Expert Solution

The Answer is B - $10,50,000

Tullis should recognize the Gross Profit of $ 10,50,000

Percentage of Completion Method

                                                                            

(A) Costs incurred to date                         $ 16,00,000

Estimated future costs                                48,00,000

(B) Estimated total costs                           64,00,000

Progress billings to date 36,00,000

Cash collected to date 35,00,000

C) Est. total gross profit (1,06,00,000-B) 42,00,000  

(D) Percent Complete (A/B)                       25%           

Total GP Recognized to Date (C*D) 10,50,000  

Current Yr. Gross Profit Recognized 10,50,000  

.

.

.

.

ALL THE BEST !!!


Related Solutions

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year.
The Young Company enters into a long-term project to build a new office building. The Contract...
The Young Company enters into a long-term project to build a new office building. The Contract price is $9,000,000 and Young expects to complete the project in three years. Young gives you the following information for the first two years regarding the project: 2017 2018 Actual costs incurred during year 2,400,000 3,800,000 Estimated costs to complete at as of December 31: 5,100,000 3,000,000 Amounts billed to customer 2,800,000 4,100,000 Collections from customer 2,600,000 3,400,000 Required: 1.    Prepare the journal entries...
A construction company entered into a fixed-price contract to build an office building for $28 million....
A construction company entered into a fixed-price contract to build an office building for $28 million. Construction costs incurred during the first year were $8 million and estimated costs to complete at the end of the year were $12 million. During the first year the company billed its customer $10 million, of which $4 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
A construction company entered into a fixed-price contract to build an office building for $38 million....
A construction company entered into a fixed-price contract to build an office building for $38 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $18 million. During the first year the company billed its customer $14 million, of which $7 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 50 $ 150 $ 45 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018   Costs incurred during the year $ 50 Estimated costs to complete as of December 31 $200 2019  Costs incurred during...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 40 $ 80 $ 50 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 70 $ 60 $ 30 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $340 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 40 $ 120 $ 50 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 70 $ 60 $ 30 Estimated costs to complete as of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT