Question

In: Accounting

Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on...

Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period:

$5,300,000, 6% note
$12,820,000, 10% bonds

Construction expenditures incurred were as follows:

March 31, 2018 $ 3,730,000
June 30, 2018 5,730,000
November 30, 2018 1,746,000
February 28, 2019 2,730,000


The company’s fiscal year-end is December 31.

Required:
Calculate the amount of interest capitalized for 2018 and 2019. (Round weighted average interest rate to 2 decimal places and final answers to the nearest whole dollar.)

Thank you in advance!

Solutions

Expert Solution

Solution:

Construction of Building
Schedule of Weighted-Average accumulated expenditure - 2018
Date Amount Current year capitalization period Weighted Average Accumulated Expenditures
31-Mar-18 $3,730,000.00 9/12 $2,797,500.00
30-Jun-18 $5,730,000.00 6/12 $2,865,000.00
30-Nov-18 $1,746,000.00 1/12 $145,500.00
$11,206,000.00 $5,808,000.00
Construction of Building
Schedule of Weighted-Average accumulated expenditure - 2019
Date Amount Current year capitalization period Weighted Average Accumulated Expenditures
Beginning balance $11,206,000.00 4/12 $3,735,333.33
28-Feb-19 $2,730,000.00 2/12 $455,000.00
$13,936,000.00 $4,190,333.33

Weighted average interest rate for captialization purpose = (6% * $5,300,000 / $18,120,000) + (10% * $12,820,000 / $18,120,000)

= 8.83%

Interest to be capitalized in 2018 = $5,808,000 * 8.83% = $512,846

Interest to be capitalized in 2019 = $4,190,333 * 8.83% = $370,006


Related Solutions

Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 31, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 6% note $16,000,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $4,000,000 June 30, 2018 6,000,000 November 30, 2018 1,800,000 February 28, 2019 3,000,000 The company's fiscal year-end is December 31. Required: Calculate the...
Hawkins Corporation began construction on a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction on a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction periods: $4,000,000 6% note $16,000,000 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $4,000,000 June 30, 2018 6,000,000 November 30, 2018 1,800,000 February 28, 2019 3,000,000 The company's fiscal year-end is December 31. Calculate the amount...
Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,100,000, 6% note $16,740,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2021 $ 4,090,000 June 30, 2021 6,090,000 November 30, 2021 1,818,000 February 28, 2022 3,090,000 The company’s fiscal year-end is December 31. Required: Calculate...
Aberforth Dumbledore Corporation began construction of a tavern on March 31, 2021. The project was completed...
Aberforth Dumbledore Corporation began construction of a tavern on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Aberforth Dumbledore had the following debts that were outstanding throughout the construction period: $4,700,000, 6% note $21,180,000, 9% bonds Construction expenditures incurred were as follows: March 31, 2021 $ 4,630,000 June 30, 2021 6,630,000 November 30, 2021 1,926,000 February 28, 2022 3,630,000 What is Aberforth Dumbledore Corporation's weighted average cost of debt?
X Company is constructing a building. Construction began in 2018 and the building was completed 31...
X Company is constructing a building. Construction began in 2018 and the building was completed 31 December, 2018. X made payments to the construction company of $1,000,000 on 1 July, $2,100,000 on 1 September, and $2,000,000 on 31 December. Average accumulated expenditures were ------. Select one: a. $5,100,000. b. $1,200,000. c. $3,100,000. d. $1,025,000. The treasury stocks should be deducted from the stockholder’s equity. Select one: a. True. b. False.
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 340,000 September 30, 2018 690,000 November 30, 2018 690,000 January 30, 2019 630,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 340,000 September 30, 2018 690,000 November 30, 2018 690,000 January 30, 2019 630,000 The company’s fiscal year-end is December 31. Required: Calculate...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows: 2018 2019 2020 Costs incurred during the year $250,000 $600,000 $190,000 Partial billings $375,000 $500,000 $375,000 Estimated costs to complete $750,000 $212,500 $0 Collections $187,500 $469,000 $593,500 Instructions: 1. Assuming Deen the percentage of completion method: (a) Prepare a schedule that computes the gross profit for 2018 - 2020 (b) Determine...
Swifty Corporation is constructing a building. Construction began on January 1 and was completed on December...
Swifty Corporation is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6480000 on March 1, $5310000 on June 1, and $8350000 on December 31. Swifty Corporation borrowed $3200000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6390000 note payable and an 11%, 4-year, $11950000 note payable. What amount of interest should be charged to...
Red Man Construction is constructing a building. Construction began on January 1 and was completed on...
Red Man Construction is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Red Man borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable prepare all entries that are necessary
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT