Question

In: Accounting

Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on...

Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 31, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period:

$4,000,000, 6% note
$16,000,000, 10% bonds

Construction expenditures incurred were as follows:

March 31, 2018 $4,000,000
June 30, 2018 6,000,000
November 30, 2018 1,800,000
February 28, 2019 3,000,000


The company's fiscal year-end is December 31.

Required:

Calculate the amount of interest capitalized for 2018 and 2019

Solutions

Expert Solution

Construction of Building
Schedule of Weighted-Average accumulated expenditure - 2018
Date Amount Current year capitalization period Weighted Average Accumulated Expenditures
31-Mar-18 $4,000,000.00 9/12 $3000000
30-Jun-18 $6,000,000.00 6/12 $3000000
30-Nov-18 $1,800,000.00 1/12 $150000
$11,800,000.00 $6,150,000.00
Construction of Building
Schedule of Weighted-Average accumulated expenditure - 2019
Date Amount Current year capitalization period Weighted Average Accumulated Expenditures
Beginning balance $11,800,000.00 4/12 $3,933,333.33
28-Feb-19 $3,000,000.00 2/12 $400,000.00
$14,800,000.00 $4,433,333.33

Weighted average interest rate for capitalization purpose = (6% * $4,000,000 / $20,000,000) + (10% * $16,000,000 / $20,000,000)

= 9.20%

Interest to be capitalized in 2018 = $6,150,000.00 * 9.20% = $565,800

Interest to be capitalized in 2019 = $4,433,333.33 * 9.20% = $407867


Related Solutions

Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $5,300,000, 6% note $12,820,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $ 3,730,000 June 30, 2018 5,730,000 November 30, 2018 1,746,000 February 28, 2019 2,730,000 The company’s fiscal year-end is December 31. Required: Calculate...
Hawkins Corporation began construction on a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction on a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction periods: $4,000,000 6% note $16,000,000 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $4,000,000 June 30, 2018 6,000,000 November 30, 2018 1,800,000 February 28, 2019 3,000,000 The company's fiscal year-end is December 31. Calculate the amount...
Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,100,000, 6% note $16,740,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2021 $ 4,090,000 June 30, 2021 6,090,000 November 30, 2021 1,818,000 February 28, 2022 3,090,000 The company’s fiscal year-end is December 31. Required: Calculate...
Aberforth Dumbledore Corporation began construction of a tavern on March 31, 2021. The project was completed...
Aberforth Dumbledore Corporation began construction of a tavern on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Aberforth Dumbledore had the following debts that were outstanding throughout the construction period: $4,700,000, 6% note $21,180,000, 9% bonds Construction expenditures incurred were as follows: March 31, 2021 $ 4,630,000 June 30, 2021 6,630,000 November 30, 2021 1,926,000 February 28, 2022 3,630,000 What is Aberforth Dumbledore Corporation's weighted average cost of debt?
X Company is constructing a building. Construction began in 2018 and the building was completed 31...
X Company is constructing a building. Construction began in 2018 and the building was completed 31 December, 2018. X made payments to the construction company of $1,000,000 on 1 July, $2,100,000 on 1 September, and $2,000,000 on 31 December. Average accumulated expenditures were ------. Select one: a. $5,100,000. b. $1,200,000. c. $3,100,000. d. $1,025,000. The treasury stocks should be deducted from the stockholder’s equity. Select one: a. True. b. False.
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 340,000 September 30, 2018 690,000 November 30, 2018 690,000 January 30, 2019 630,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 340,000 September 30, 2018 690,000 November 30, 2018 690,000 January 30, 2019 630,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 340,000 September 30, 2018 690,000 November 30, 2018 690,000 January 30, 2019 630,000 The company’s fiscal year-end is December 31. Required: Calculate...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows: 2018 2019 2020 Costs incurred during the year $250,000 $600,000 $190,000 Partial billings $375,000 $500,000 $375,000 Estimated costs to complete $750,000 $212,500 $0 Collections $187,500 $469,000 $593,500 Instructions: 1. Assuming Deen the percentage of completion method: (a) Prepare a schedule that computes the gross profit for 2018 - 2020 (b) Determine...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 10% note $7,000,000, 6% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 460,000 September 30, 2021 660,000 November 30, 2021 660,000 January 30, 2022 600,000 The company’s fiscal year-end is December 31. Required: Calculate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT