Question

In: Accounting

Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period:

$3,000,000, 10% note
$7,000,000, 6% bonds


Construction expenditures incurred were as follows:

July 1, 2021 $ 460,000
September 30, 2021 660,000
November 30, 2021 660,000
January 30, 2022 600,000


The company’s fiscal year-end is December 31.

Required:
Calculate the amount of interest capitalized for 2021 and 2022.

Solutions

Expert Solution

a) Interest Capitalized for 2021
Date Expenditure Weight Average
Jul 1, 2021 $460,000 x 0.5 = $230,000
Sep 30, 2021 $660,000 x 0.25 = $165,000
Nov 30, 2021 $660,000 x 0.083 = $54,780
Accumulated Expenditures $1,780,000 $449,780
Amount Interest Rate Capitalized Interest
Average Accumulated Expenditures $449,780 7.20% $32,384
Weighted Average interest rate
$3,000,000, 10% note $300,000
$7,000,000, 6% bonds $420,000
$720,000
Weighted rate = $720,000/($3,000,000 + $7,000,0000 7.20%
b) Interst capitalized for 2022
Date Expenditure Weight Average
Jan 1, 2022 $1,812,384 x 1 = $1,812,384
Jan 31, 2022 $600,000 x 0.889 = $533,400
Accumulated Expenditures $2412,384 $2,345,784
Bal .on jan1 2022 ($1,780,000+$32384) $1,812,384
Amount Interest Rate Capitalized Interest 2022
Average Accumulated Expenditures $2,345,784 7.20% $168,896

if any doubt kindly mention in comment


Related Solutions

Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 340,000 September 30, 2018 690,000 November 30, 2018 690,000 January 30, 2019 630,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 340,000 September 30, 2018 690,000 November 30, 2018 690,000 January 30, 2019 630,000 The company’s fiscal year-end is December 31. Required: Calculate...
Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,100,000, 6% note $16,740,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2021 $ 4,090,000 June 30, 2021 6,090,000 November 30, 2021 1,818,000 February 28, 2022 3,090,000 The company’s fiscal year-end is December 31. Required: Calculate...
On April 1, 2020, Dalinar Company began construction on a new distribution warehouse. Construction was completed...
On April 1, 2020, Dalinar Company began construction on a new distribution warehouse. Construction was completed on December 31, 2020, at which time the building was placed in service. Dalinar made an initial payment toward construction on April 1, 2020 of $240,000 and made additional payments $30,000 every two months thereafter, beginning on June 1 and continuing through December 1. A final payment of $100,000 was made on December 31 at the completion of construction. Dalinar borrowed $150,000 at 4%...
Aberforth Dumbledore Corporation began construction of a tavern on March 31, 2021. The project was completed...
Aberforth Dumbledore Corporation began construction of a tavern on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Aberforth Dumbledore had the following debts that were outstanding throughout the construction period: $4,700,000, 6% note $21,180,000, 9% bonds Construction expenditures incurred were as follows: March 31, 2021 $ 4,630,000 June 30, 2021 6,630,000 November 30, 2021 1,926,000 February 28, 2022 3,630,000 What is Aberforth Dumbledore Corporation's weighted average cost of debt?
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 326,000 September 1, 2021 $ 477,000 December 31, 2021 $ 477,000 March 31, 2022 $ 477,000 September 30, 2022 $ 326,000 Dreamworld had $5,900,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
Bonita Industries is constructing a building. Construction began on January 1 and was completed on December...
Bonita Industries is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6552000 on March 1, $5280000 on June 1, and $8450000 on December 31. Bonita Industries borrowed $3180000 on January 1 on a 5-year, 10% note to help finance construction of the building. In addition, the company had outstanding all year a 8%, 3-year, $6410000 note payable and an 9%, 4-year, $12150000 note payable. What are the weighted-average accumulated expenditures? a.20282000 b.8540000...
Villa Industries is constructing a building. Construction began on January 1 and was completed on December...
Villa Industries is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6370000 on March 1, $5300000 on June 1, and $8250000 on December 31. Bonita Industries borrowed $3250000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6450000 note payable and an 11%, 4-year, $12250000 note payable. What is the actual interest for Bonita Industries?...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $58.5 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $90 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $64 million...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT