Question

In: Accounting

Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period:

$2,000,000, 7% note
$8,000,000, 3% bonds


Construction expenditures incurred were as follows:

July 1, 2018 $ 340,000
September 30, 2018 690,000
November 30, 2018 690,000
January 30, 2019 630,000


The company’s fiscal year-end is December 31.

Required:
Calculate the amount of interest capitalized for 2018 and 2019.

Solutions

Expert Solution

Answer

Interest Capitalized for 2018

Date Expenditure Weight Average
01-Jul-18 $        3,40,000 0.5 $    1,70,000
30-Sep-18 $        6,90,000 0.25 $    1,72,500
30-Nov-18 $        6,90,000 0.08 $       55,200
Accumulated   Expenditures $      17,20,000 $    3,97,700
Weighted Average rate = 380,000/10,000,000=3.8%
Interest Capitalized for 2018 = 3,97,700 x 3.80% = 15,112.6
Interest Capitalized for 2019
Date Expenditure Weight Average
01-Jan-19 17,35,112.60 1 17,35,112.60
31-Jan-19 $        6,30,000 0.889 $    5,60,070
Accumulated   Expenditures 23,65,112.60 22,95,182.60
Interest Capitalized for 2019 = 22,95,182.60 x 3.80% = 87216.94

Related Solutions

Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 340,000 September 30, 2018 690,000 November 30, 2018 690,000 January 30, 2019 630,000 The company’s fiscal year-end is December 31. Required: Calculate...
On April 1, 2020, Dalinar Company began construction on a new distribution warehouse. Construction was completed...
On April 1, 2020, Dalinar Company began construction on a new distribution warehouse. Construction was completed on December 31, 2020, at which time the building was placed in service. Dalinar made an initial payment toward construction on April 1, 2020 of $240,000 and made additional payments $30,000 every two months thereafter, beginning on June 1 and continuing through December 1. A final payment of $100,000 was made on December 31 at the completion of construction. Dalinar borrowed $150,000 at 4%...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $5,300,000, 6% note $12,820,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $ 3,730,000 June 30, 2018 5,730,000 November 30, 2018 1,746,000 February 28, 2019 2,730,000 The company’s fiscal year-end is December 31. Required: Calculate...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 31, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 6% note $16,000,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $4,000,000 June 30, 2018 6,000,000 November 30, 2018 1,800,000 February 28, 2019 3,000,000 The company's fiscal year-end is December 31. Required: Calculate the...
Hawkins Corporation began construction on a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction on a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction periods: $4,000,000 6% note $16,000,000 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $4,000,000 June 30, 2018 6,000,000 November 30, 2018 1,800,000 February 28, 2019 3,000,000 The company's fiscal year-end is December 31. Calculate the amount...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $50,000 None...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 336,000 September 1, 2018 $ 504,000 December 31, 2018 $ 504,000 March 31, 2019 $ 504,000 September 30, 2019 $ 336,000 Dreamworld had $6,800,000 in 10% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT