Question

In: Accounting

Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated...

Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows:

2018 2019 2020
Costs incurred during the year $250,000 $600,000 $190,000
Partial billings $375,000 $500,000 $375,000
Estimated costs to complete $750,000 $212,500 $0
Collections $187,500 $469,000 $593,500

Instructions:

1. Assuming Deen the percentage of completion method:

(a) Prepare a schedule that computes the gross profit for 2018 - 2020

(b) Determine the net amount for construction in progress inventory should be reported on the 2018 balance sheet.

(c) Prepare all the necessary journal entries for 2019

2. Compute the amount of gross profit to be recognized each year, assuming the completed contract method is used.

You must show supporting computations to receive credit.

Solutions

Expert Solution

Answer:
1.(a) Computation of % of completion, revenue recognition and Gross Profit - Deen Construction
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G-A)
(E)
2018 $250,000 $250,000 $1,000,000 25.00% $1,250,000 $312,500 $312,500 $62,500
2019 $600,000 $850,000 $1,062,500 80.00% $1,250,000 $1,000,000 $687,500 $87,500
2020 $190,000 $1,040,000 $1,040,000 100.00% $1,250,000 $1,250,000 $250,000 $60,000
1.(b)
Net amount of construction in progress inventory to be reported in 2018 balance sheet = Revenue recognized - Billing done
= $312,500 - $375,000 = ($62,500)
1.(c) Journal Entries - Deen Construction- 2019
1 Construction in Progress Dr $600,000.00
       To Various Accounts $600,000.00
(To record construction cost incurred)
2 Accounts receivables Dr $500,000.00
       To Billings on construction contract $500,000.00
(To record progress billings)
3 Cash Dr $469,000.00
       To Accounts receivables $469,000.00
(To record collection from customer)
4 Construction in Progress Dr $87,500.00
Cost of construction Dr $600,000.00
       To Revenue from long term contracts $687,500.00
(To record revenue and gross profit)
2) Computation of Gross Profit - Revenue on completion -Deen Construction Company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price Gross Profit
(D)
2018 $250,000 $250,000 $1,000,000 $1,250,000 $0
2019 $600,000 $850,000 $1,062,500 $1,250,000 $0
2020 $190,000 $1,040,000 $1,040,000 $1,250,000 $210,000.00

Related Solutions

Indiana Co. began a construction project in 2016 with a contract price of $150 million to...
Indiana Co. began a construction project in 2016 with a contract price of $150 million to be received when the project is completed in 2018. During 2016, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2017, Indiana incurred additional costs of $63.75 million...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $58.5 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $90 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $64 million...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $38 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Indiana: A. Recognized no gross profit or loss on the project...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $39 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $59 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $57 million and estimated...
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:         ...
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:          2020                           2021          Costs incurred to date......................................................................      $ 540,000                 $ 875,000          Estimated costs to complete as of December 31.................         360,000 100,000          Billings to date.....................................................................................         420,000 950,000          Collections to date.............................................................................         300,000 700,000 Classical uses the percentage-of-completion method. Gross profit recognized in 2020 was $210,000 (Revenue $750,000; expense $540,000). The 2020 opening balance on LT Contract Asset/Liab is...
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:         ...
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:          2020                           2021          Costs incurred to date......................................................................      $ 540,000                 $ 875,000          Estimated costs to complete as of December 31.................         360,000 100,000          Billings to date.....................................................................................         420,000 950,000          Collections to date.............................................................................         300,000 700,000 Classical uses the percentage-of-completion method. Gross profit recognized in 2020 was $210,000 (Revenue $750,000; expense $540,000). The 2020 opening balance on LT Contract Asset/Liab is $330,000...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT