Question

In: Accounting

Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on...

Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period:

$4,100,000, 6% note
$16,740,000, 10% bonds

Construction expenditures incurred were as follows:

March 31, 2021 $ 4,090,000
June 30, 2021 6,090,000
November 30, 2021 1,818,000
February 28, 2022 3,090,000


The company’s fiscal year-end is December 31.

Required:
Calculate the amount of interest capitalized for 2021 and 2022. (Round weighted average interest rate to 2 decimal places and final answers to the nearest whole dollar.)

Solutions

Expert Solution

Calculation of Interest amount Capitalized During 2021 & 2022
Date No of Months Amount Interest
@9.21%
April 1st 2021 12 $       40,90,000 $       3,76,814
June 30th 2021 9 $       60,90,000 $       4,20,806
November 30th 2021 4 $       18,18,000 $           55,831
Feb 28th 2022 1 $       30,90,000 $           23,724
$   1,50,88,000 $       8,77,175
Interest Capitalized During 2021 is $       8,77,175
Interest Capitalized During 20212 is $       1,15,839
Interest Expended*1month*9.21%
15088000*9.21%*1/12
$         1,15,839
Calaculation of Weighted Average Borrowing Rate
Loan Rate Interest
$       41,00,000 6% $         2,46,000
$   1,67,40,000 10% $       16,74,000
$   2,08,40,000 $       19,20,000
W.Average Int Rate = Total Interest/Total Loan
=1920000/20840000
9.21%

Related Solutions

Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $5,300,000, 6% note $12,820,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $ 3,730,000 June 30, 2018 5,730,000 November 30, 2018 1,746,000 February 28, 2019 2,730,000 The company’s fiscal year-end is December 31. Required: Calculate...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 31, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 6% note $16,000,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $4,000,000 June 30, 2018 6,000,000 November 30, 2018 1,800,000 February 28, 2019 3,000,000 The company's fiscal year-end is December 31. Required: Calculate the...
Hawkins Corporation began construction on a motel on March 31, 2018. The project was completed on...
Hawkins Corporation began construction on a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction periods: $4,000,000 6% note $16,000,000 10% bonds Construction expenditures incurred were as follows: March 31, 2018 $4,000,000 June 30, 2018 6,000,000 November 30, 2018 1,800,000 February 28, 2019 3,000,000 The company's fiscal year-end is December 31. Calculate the amount...
Aberforth Dumbledore Corporation began construction of a tavern on March 31, 2021. The project was completed...
Aberforth Dumbledore Corporation began construction of a tavern on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Aberforth Dumbledore had the following debts that were outstanding throughout the construction period: $4,700,000, 6% note $21,180,000, 9% bonds Construction expenditures incurred were as follows: March 31, 2021 $ 4,630,000 June 30, 2021 6,630,000 November 30, 2021 1,926,000 February 28, 2022 3,630,000 What is Aberforth Dumbledore Corporation's weighted average cost of debt?
X Company is constructing a building. Construction began in 2018 and the building was completed 31...
X Company is constructing a building. Construction began in 2018 and the building was completed 31 December, 2018. X made payments to the construction company of $1,000,000 on 1 July, $2,100,000 on 1 September, and $2,000,000 on 31 December. Average accumulated expenditures were ------. Select one: a. $5,100,000. b. $1,200,000. c. $3,100,000. d. $1,025,000. The treasury stocks should be deducted from the stockholder’s equity. Select one: a. True. b. False.
ndiana Co. began a construction project in 2021 with a contract price of $150 million to...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $58.5 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $90 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $64 million...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $38 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Indiana: A. Recognized no gross profit or loss on the project...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $39 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $59 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $57 million and estimated...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT