In: Accounting
Indiana Co. began a construction project in 2021 with a contract
price of $163 million to be received when the project is completed
in 2023. During 2021, Indiana incurred $39 million of costs and
estimates an additional $81 million of costs to complete the
project. Indiana recognizes revenue over time and for this project
recognizes revenue over time according to the percentage of the
project that has been completed.
In 2022, Indiana incurred additional costs of $59 million and
estimated an additional $36 million in costs to complete the
project. Indiana (Do not round your percentage
calculated):
Multiple Choice
Recognized $4.00 million gross profit on the project in 2022.
Recognized $27.50 million gross profit on the project in 2022.
Recognized $7.23 million gross profit on the project in 2022.
Recognized $29.00 million gross profit on the project in 2022.
Dear Friend,
We need to calculate this by following percentage of completion method year by year, so lets calculate total revenue we recognized in 2021:
Total Contract Value = $163 million
Cost incurred in 2021 = $39 million
cost to be incurred in future = $81 million
Total cost to complete the project = $120 million
Percentage of completion = 39/120 = 32.5%
Revenue recognized till 2021 = $163*32.5% = $52.975 million
Now, lets calculate total revenue we recognized in 2022:
Cost incurred in 2021 = $39 million
Cost incurred in 2022 = $59 million
Total cost incurred till date = 39+59 = $98 million
cost to be incurred in future = $36 million
Total cost to complete the project = $98+36 = $134 million
Percentage of completion = 98/134 = 73.13%
Revenue recognized till 2022 (including 2021) = $163*73.13% = $119.209 million
So, Revenue recognized only in 2022 = 119.209-52.975 = 66.234 million
Cost incurred in only 2022 = 59 million
Gross Profit in 2022 = 66.234-59 = 7.234 Millions (option C)