Question

In: Accounting

ndiana Co. began a construction project in 2021 with a contract price of $150 million to...

ndiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.

In 2022, Indiana incurred additional costs of $58.5 million and estimated an additional $40.5 million in costs to complete the project. Indiana:

A. Recognized $15 million gross profit on the project in 2022.

B. Recognized $13.5 million gross profit on the project in 2022.

C. Recognized $6 million gross profit on the project in 2022.

D. Recognized $1.5 million gross profit on the project in 2022.

Solutions

Expert Solution

  • Correct Answer = Option ‘D’ Recognise $ 1.50 millions gross profit in 2022
  • Working

>Amount is in $ millions

Working

Year end 2021

Year end 2022

A

Contract Price

$                   150.00

$                   150.00

B

Cost Incurred to Date

$                     36.00

$                     94.50 [36 + 58.50]

C

Estimated cost yet to be incurred to complete the contract

$                     84.00

$                     40.50

D = B+C

Total Cost

$                   120.00

$                   135.00

E = (B/D) x 100

% of Completion

30.00%

70.00%

F = A x E

Revenue to date

$                     45.00

$                   105.00

G

Revenue of Previous year

$                            -  

$                     45.00

H = F - G

Net Revenue this year

$                     45.00

$                     60.00

I (=B)

Cost to date

$                     36.00

$                     94.50

J

Cost to date of previous year

$                            -  

$                     36.00

K = I - J

Net Cost for the year

$                     36.00

$                     58.50

L = H - K

Gross Profits

$                        9.00

$                       1.50 ANSWER


Related Solutions

Indiana Co. began a construction project in 2016 with a contract price of $150 million to...
Indiana Co. began a construction project in 2016 with a contract price of $150 million to be received when the project is completed in 2018. During 2016, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2017, Indiana incurred additional costs of $63.75 million...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $90 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $64 million...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $38 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Indiana: A. Recognized no gross profit or loss on the project...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $39 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $59 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $57 million and estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows: 2018 2019 2020 Costs incurred during the year $250,000 $600,000 $190,000 Partial billings $375,000 $500,000 $375,000 Estimated costs to complete $750,000 $212,500 $0 Collections $187,500 $469,000 $593,500 Instructions: 1. Assuming Deen the percentage of completion method: (a) Prepare a schedule that computes the gross profit for 2018 - 2020 (b) Determine...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on...
Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,100,000, 6% note $16,740,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2021 $ 4,090,000 June 30, 2021 6,090,000 November 30, 2021 1,818,000 February 28, 2022 3,090,000 The company’s fiscal year-end is December 31. Required: Calculate...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 326,000 September 1, 2021 $ 477,000 December 31, 2021 $ 477,000 March 31, 2022 $ 477,000 September 30, 2022 $ 326,000 Dreamworld had $5,900,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT