Question

In: Accounting

Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...

Long-term Contracts

Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows:

2017 2018
Costs incurred during the year $ 600,000 $ 700,000
Estimated costs to complete, December 31 $1,400,000 $1,200,000
Billings during the year $500,000 $850,000
Collections during the year $400,000 $800,000

Required:

1. Compute the gross profit or loss recognized in 2017 and 2018.

KOOLMAN CONSTRUCTION COMPANY
Gross Profit / Loss
2017 and 2018
2017 2018
Construction costs incurred to date $ $
Estimated costs to complete $ $
Total estimated costs $ $
Percentage completed % %
Revenue to date $ $
Revenue recognized in current year $ $
Costs incurred in current year
Profit (loss) recognized $ $

2. Prepare the appropriate sections of the income statement for each year.

KOOLMAN CONSTRUCTION COMPANY
Partial Income Statement
For the Years Ended December 31, 2017 and 2018
2017 2018
Construction revenue $ $
Construction expense
Gross profit (loss) $ $

Prepare the appropriate sections of the ending balance sheet for the year 2017.

KOOLMAN CONSTRUCTION COMPANY
Partial Balance Sheet
December 31, 2017
Current Assets:
Accounts receivable $
Inventory:
Construction in progress $
Less: Partial billings
Costs and recognized profit not yet billed

Prepare the appropriate sections of the ending balance sheet for 2018.

KOOLMAN CONSTRUCTION COMPANY
Partial Balance Sheet
December 31, 2018
Current Assets:
Accounts receivable $
Inventory:
Construction in progress $
Less: Partial billings
Costs and recognized profit not yet billed

Solutions

Expert Solution

KOOLMAN CONSTRUCTION COMPANY
Gross Profit / Loss
2017 and 2018
2017 2018
Costs incurred to date 600000 1300000
Estimated costs to complete the contract 1400000 1200000
Total Estimated costs 2000000 2500000
Percentage completed 30% 52%
Revenue to Date 900000 1560000
Revenue recognized in current year 900000 660000
Costs incurred in current year 600000 700000
Profit/ (loss) recognized 300000 -40000
KOOLMAN CONSTRUCTION COMPANY
Partial income statement
For the years ended December 31, 2017 and December 31, 2018
2017 2018
Construction Revenue 900000 660000
Construction Expense 600000 700000
Gross Profit / (Loss) 300000 -40000
KOOLMAN CONSTRUCTION COMPANY
Partial Balance Sheet
as at December 31, 2017 and December 31, 2018
2017 2018
Current Assets:
Accounts Receivable 100000 150000
Inventory :
    Construction in progress 900000 1560000
    Less: Partial Billings -500000 -1350000
    Costs and recognized profits not yeat billed 400000 210000

Related Solutions

Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred costs of $280,300, billed its customer for $216,200, and collected $176,500. At December 31, 2017, the estimated additional costs to complete the project total $162,000. Prepare Waterway’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred...
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred costs of $277,100, billed its customer for $215,200, and collected $173,900. At December 31, 2017, the estimated additional costs to complete the project total $161,000. Prepare Swifty’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Trillium Construction Company is a publicly traded company that began a long-term government contract on July...
Trillium Construction Company is a publicly traded company that began a long-term government contract on July 1, 2019 to build a housing complex for the price of $8,000,000. The construction was expected to take 24 months to complete. a.       For the year ended December 31, 2019, Trillium incurred construction costs of $1,300,000 and it was estimated that an additional $3,900,000 in costs would needed to complete the contract. Trillium billed the government $2,000,000 during the first year and collected $1,000,000 by...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 Prepare a complete set of journal entries for 2017 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is...
2. The completed contract method of accounting for long-term construction-type contracts is preferable when: Select one:...
2. The completed contract method of accounting for long-term construction-type contracts is preferable when: Select one: a. Estimates of costs to complete and extent of progress toward completion are reasonably dependable. b. The contracts are of a relatively long duration. c. Lack of dependable estimates or inherent hazards cause forecasts to be doubtful d. A contractor is involved in numerous projects. 3. In preparing the adjusting journal entries for Year 4, the accountant for a large local law firm discovered...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred costs of $292,500, billed its customer for $213,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $161,340. Prepare Tamarisk’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT