Question

In: Accounting

Indiana Co. began a construction project in 2016 with a contract price of $150 million to...

Indiana Co. began a construction project in 2016 with a contract price of $150

million to be received when the project is completed in 2018. During 2016, Indiana

incurred $36 million of costs and estimates an additional $84 million of costs to

complete the project. Indiana recognizes revenue over time and for this project

recognizes revenue over time according to the percentage of the project that has

been completed.

Suppose that, in 2017, Indiana incurred additional costs of $63.75 million and

estimated an additional $42.75 million in costs to complete the project. What profit

or loss will Indiana record for 2017?

Solutions

Expert Solution

For Long term construction contracts, under percentage of completion method, the Project gain is
recognized over the project period based on the proportion of costs incurred to date to the Estimated costs

of the project.

(Figures in millions)
Particulars 2016 2017 Calculation
A. Costs incurred to date $      36.00 $ 99.75 Given for 2016; For 2017, costs of 2016 and additional costs of 2017 ie. 36 plus 63.75 gives the cost incurred till date
B. Estimated costs to complete $      84.00 $ 42.75 Given
C. Estimated total cost $    120.00 $ 142.50 A plus B
D. % Complete 30.00% 70.00% A / C
E. Cost incurred during the year $      36.00 $ 63.75 Given
F. Project Revenue $    150.00 $ 150.00 Given
G. Revenue to be recognized during the year $      45.00 $ 60.00 For 2016, Project revenue * Percent complete ie. D*F; For 2017, it is D*F minus revenue already recognized till 2016 ie.45
(150*30%) (150*70%)-45
K. Profit or (loss) recognized $         9.00 $ (3.75) G-E
Thus, loss of $ 3.75 million will be recognized by Indiana for 2017 with respect to this project.

Related Solutions

Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $90 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $64 million...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $38 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Indiana: A. Recognized no gross profit or loss on the project...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $39 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $59 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $57 million and estimated...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $58.5 million and estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows: 2018 2019 2020 Costs incurred during the year $250,000 $600,000 $190,000 Partial billings $375,000 $500,000 $375,000 Estimated costs to complete $750,000 $212,500 $0 Collections $187,500 $469,000 $593,500 Instructions: 1. Assuming Deen the percentage of completion method: (a) Prepare a schedule that computes the gross profit for 2018 - 2020 (b) Determine...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
Belgium Co. is constructing a tunnel for 800 million. Construction began in 2011 and is estimated...
Belgium Co. is constructing a tunnel for 800 million. Construction began in 2011 and is estimated to be completed in 2016. At December 31, 2013, Belgium has incurred costs totaling 356 million with 85 million of that incurred in 2013, 143 in 2012, and 128 in 2011. Belgium received 356 million in total progress payments to date but future activity is tenuous and its cost numbers are highly uncertain. What amount of revenue should Belgium Co. recognize for the year...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT