In: Finance
Basic scenario analysis Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.
Project A |
Project B |
|
Initial investment
(CF 0CF0) |
$12,700 |
$12,700 |
Outcome |
Annual cash inflows
(CFCF ) |
|
Pessimistic |
$880 |
$1,530 |
Most likely |
1,680 |
1,680 |
Optimistic |
2,470 |
1,710 |
a. Determine the range of annual cash inflows for each of the two projects.
b. Assume that the firm's cost of capital is 10.5% and that both projects have 20-year lives. Construct a table showing the NPVs for each project for each of the possible outcomes. Include the range of NPVs for each project.
c. Do parts (a) and (b)provide consistent views of the two projects? Explain.
d. Which project do you recommend? Why?
(A) Range of cash inflow of each project
project A : $ 880 - $ 2470
project B : $ 1530 - $ 1710
(B) NPV of each project
Project A
if pessimistic
year |
inflow | cumulative pv factor @ 10.5% | present value |
0 | (12700) | 1.00 | (12700) |
1 - 20 | $ 880 | 8.230 | 7242.40 |
NPV | (5457.60) |
if most likely
year |
inflow | cumulative pv factor @ 10.5% | present value |
0 | (12700) | 1.00 | (12700) |
1 - 20 | $ 1680 | 8.230 | 13826.40 |
NPV | 1126.40 |
if optimistic
year |
inflow | cumulative pv factor @ 10.5% | present value |
0 | (12700) | 1.00 | (12700) |
1 - 20 | $ 2470 | 8.230 | 20328.10 |
NPV | 7628.10 |
Project B
if pessimistic
year |
inflow | cumulative pv factor @ 10.5% | present value |
0 | (12700) | 1.00 | (12700) |
1 - 20 | $ 1530 | 8.230 | 12591.90 |
NPV | (108.10) |
if most likely
year |
inflow | cumulative pv factor @ 10.5% | present value |
0 | (12700) | 1.00 | (12700) |
1 - 20 | $ 1680 | 8.230 | 13826.40 |
NPV | 1126.40 |
if Optimistic
year |
inflow | cumulative pv factor @ 10.5% | present value |
0 | (12700) | 1.00 | (12700) |
1 - 20 | $ 1710 | 8.230 | 14073.30 |
NPV | 1373.30 |
Range of NPV
Project A : $ (5457.60) to $ 7628.10
Project B : $ (108.10) to $ 1373.30
(C) yes above part (A) and (B) is in cosistent view because following same policies in each year.
(D) Recommendation : here project A,s NPV range is good than project B , it seems that project A is more risky than project B . if company wants to take risk than project A is better and if company does,t wants to take risk than project B is better