Question

In: Finance

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.

Project A

Project B

Initial investment

​(CF 0CF0​)

​$12,700

​$12,700

Outcome

Annual cash inflows

​(CFCF ​)

Pessimistic

​$880

​$1,530

Most likely

1,680

1,680

Optimistic

2,470

1,710

a. Determine the range of annual cash inflows for each of the two projects.

b. Assume that the​ firm's cost of capital is 10.5% and that both projects have 20​-year lives. Construct a table showing the NPVs for each project for each of the possible outcomes. Include the range of NPVs for each project.

c. Do parts ​(a​) and (b​)provide consistent views of the two​ projects? Explain.

d. Which project do you​ recommend? Why?

Solutions

Expert Solution

(A) Range of cash inflow of each project

project A : $ 880 - $ 2470

project B : $ 1530 - $ 1710

(B) NPV of each project

Project A

if pessimistic

year

inflow cumulative pv factor @ 10.5% present value
0 (12700) 1.00 (12700)
1 - 20 $ 880 8.230 7242.40
NPV (5457.60)

if most likely

year

inflow cumulative pv factor @ 10.5% present value
0 (12700) 1.00 (12700)
1 - 20 $ 1680 8.230 13826.40
NPV 1126.40

if optimistic

year

inflow cumulative pv factor @ 10.5% present value
0 (12700) 1.00 (12700)
1 - 20 $ 2470 8.230 20328.10
NPV 7628.10

Project B

if pessimistic

year

inflow cumulative pv factor @ 10.5% present value
0 (12700) 1.00 (12700)
1 - 20 $ 1530 8.230 12591.90
NPV (108.10)

if most likely

year

inflow cumulative pv factor @ 10.5% present value
0 (12700) 1.00 (12700)
1 - 20 $ 1680 8.230 13826.40
NPV 1126.40

if Optimistic

year

inflow cumulative pv factor @ 10.5% present value
0 (12700) 1.00 (12700)
1 - 20 $ 1710 8.230 14073.30
NPV 1373.30

Range of NPV

Project A : $ (5457.60) to $ 7628.10

Project B : $ (108.10) to $ 1373.30

(C) yes above part (A) and (B) is in cosistent view because following same policies in each year.

(D) Recommendation : here project A,s NPV range is good than project B , it seems that project A is more risky than project B . if company wants to take risk than project A is better and if company does,t wants to take risk than project B is better


Related Solutions

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash inflows...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​12,200 ​12,200 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$800 ​$1,560 Most likely 1,700 1,700 Optimistic 2,480 1,720 a. Determine the range of...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​ $12,900    ​ $12,900    Outcome Annual cash inflows ​(CF ​) Pessimistic ​$870 ​$1,530 Most likely 1,690 1,690 Optimistic 2,500 1 720 a. Determine...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,800 ​$12,800 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$860 ​$1,530 Most likely 1,680 1,680 Optimistic 2,500 1,780 a. Determine the range of annual cash...
Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity.
Project AProject BInitial investment(CF0)$12,600$12,600OutcomeAnnual cash inflows(CF )Pessimistic$810$1,590Most likely1,6101,610Optimistic2,4901,770Basic scenario analysis  Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.a. Determine the range of annual cash inflows for each of the two projects.b. Assume that the firm's cost of capital is 9.5% and that both...
P12-4 (similar to) Basic scenario analysis   Prime Paints is in the process of evaluating two mutually...
P12-4 (similar to) Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment 12,500 12,500 ​(CF 0CF0​) Outcome Annual cash inflows ​(CF CF ​) Pessimistic ​$880 ​$1,550 Most likely 1,690 1,690 Optimistic 2,420 1,790 a. Determine...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT