Question

In: Finance

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.

Project A

Project B

Initial investment

​(CF 0CF0​)

​$12,800

​$12,800

Outcome

Annual cash inflows

​(CFCF ​)

Pessimistic

​$860

​$1,530

Most likely

1,680

1,680

Optimistic

2,500

1,780

a. Determine the range of annual cash inflows for each of the two projects.

b. Assume that the​ firm's cost of capital is 10.4% and that both projects have 17​-year

lives. Construct a table showing the NPVs for each project for each of the possible outcomes. Include the range of NPVs for each project.

c. Do parts ​(a​) and ​(b​)

provide consistent views of the two​ projects? Explain

d. Which project do you​ recommend? Why?

Solutions

Expert Solution

Ans a) Range of annual cash inflows for each of the two projects.

Range is the difference between highest and lowest value in the data set.

Project A – Range of Project A

Highest – Lowest = 2500 – 860 = 1640

Project Lifetime Range = 1640 * 17 (No of Years) = 27880

Project B – Range of Project B

Highest – Lowest = 1780 – 1530 = 250

Project Lifetime Range = 250 * 17 (No of Years) = 4250

Ans b) NPV and Range of NPV

Cost of Capital = 10.4%

Number of Years = 17Years

As cash flow amount is consistent for 17 years in both the period and in every scenario so we can use Present Value of Annuity formula to calculate present value and net present value.

Net Present Value = Cash Flow * (1- ((1+r)^-n) / r) – Initial Investment

Project A – Initial Cost = 12800

Pessimistic = ((860*(1- ((1+0.104)^-17)) /0.104) – 12800) = - 6,068.89

Most likely = ((1680*(1- ((1+0.104)^-17)) /0.104) – 12800) = 349.14

Optimistic = ((2500*(1- ((1+0.104)^-17)) /0.104) – 12800) = 6767.18

Project A NPV Range = 6767.18 – (-6068.89) = 12836.07

Project B – Initial Cost = 12800

Pessimistic = ((1530*(1- ((1+0.104)^-17)) /0.104) – 12800) = -433.54

Most likely = ((1680*(1- ((1+0.104)^-17)) /0.104) – 12800) = 349.14

Optimistic = ((1780*(1- ((1+0.104)^-17)) /0.104) – 12800) = 1131.83

Project B NPV Range = 1131.83-(-433.54) = 1565.37

Ans c) Project A with high range of both Cash Flow and NPV is more volatile than Project B. We can see clear difference in Pessimistic and Optimistic situation where Project A is highly volatile in case of free cash flow however Project B is more stable, whereas both have same cash flow in most likely scenario. So Project B is considered to be more safe.

Ans d) I would recommend Project B as even if project experience Pessimistic situation our losses are very restricted where as Project A can be a big loss making deal in Pessimistic situation. Project B is less risky than Project A.

Hope this helps . Thanks !! Feel free to share your views.


Related Solutions

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,700 ​$12,700 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$880 ​$1,530 Most likely 1,680 1,680 Optimistic 2,470 1,710 a. Determine the range of annual...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash inflows...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​12,200 ​12,200 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$800 ​$1,560 Most likely 1,700 1,700 Optimistic 2,480 1,720 a. Determine the range of...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​ $12,900    ​ $12,900    Outcome Annual cash inflows ​(CF ​) Pessimistic ​$870 ​$1,530 Most likely 1,690 1,690 Optimistic 2,500 1 720 a. Determine...
Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity.
Project AProject BInitial investment(CF0)$12,600$12,600OutcomeAnnual cash inflows(CF )Pessimistic$810$1,590Most likely1,6101,610Optimistic2,4901,770Basic scenario analysis  Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.a. Determine the range of annual cash inflows for each of the two projects.b. Assume that the firm's cost of capital is 9.5% and that both...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT