Question

In: Finance

Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to...

Basic scenario analysis  

 Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.

Project A Project B
Initial investment

​(CF0​)

​ $12,900   

​ $12,900   

Outcome

Annual cash inflows

​(CF ​)

Pessimistic

​$870

​$1,530

Most likely

1,690

1,690

Optimistic

2,500

1 720

a. Determine the range of annual cash inflows for each of the two projects.

b. Assume that the​ firm's cost of capital is 9.2 % and that both projects have 19​-year lives. Construct a table showing the NPVs for each project for each of the possible outcomes. Include the range of NPVs for each project

. c. Do parts ​(a​) and ​(b​) provide consistent views of the two​ projects? Explain. d. Which project do you​ recommend? Why?

Solutions

Expert Solution

A.The Range of Annual cash flow

For Project A- $ 870- $ 2500
For Project B - $ 1530 - $ 1720

B.

Calculation of discounted cash flows for each possible outcome of the project
Project A Project B
Particulars Amount ( $) Present value factor of Annuity @ 9.2% Discounted Cash Flows Amount ( $) Present value factor of Annuity @ 9.2% Discounted Cash Flows
1 2 3 4(2*3) 5 6 7(5*6)
Pesimistic $870 8.8279 $7,680.27 $1,530 8.8279 $13,506.69
Most likely $1,690 8.8279 $14,919.15 $1,690 8.8279 $14,919.15
Optimistic $2,500 8.8279 $22,069.75 $1,720 8.8279 $15,183.99

B.Calculation of Net present value for each possible outcome of the project.

Project A Project - B
Particulars Pesimistic Most likely Optimistic Pesimistic Most likely Optimistic
A.Total income genereated from the project ( Step 1) $7,680.27 $14,919.15 $22,069.75 $13,506.69 $14,919.15 $15,183.99
B.Initial outlay of the Project $12,900 $12,900 $12,900 $12,900 $12,900 $12,900
C.Net Present Value ($5,219.73) $2,019.15 $9,169.75 $606.69 $2,019.15 $2,283.99

NPV Range for Project A - ( $ 5219.73) To $ 9169.7
Project B - $ 606.69 To $ 2283.99

C.If the outcome is in the point of view of Pessimistic then the project A is not at all viable,because the project will lead to as end up of Negative NPV of $5219.73.In case of Project B , even in case of pessimestic view also the projects ends up with a positive NPV of $ 606.69. In case the outcome islikely we can accept any project since both are giving an positive outcommf poe of $ 2019.15. In case optimistic outcome project A is more viable since taking up this project involve higher positive NPV than B.

D.I would recommend project B because irrespective of the outcome,the result end up in a positive NPV.

In case of investor is risk averse and highly possessing a optmistic outcome than i would recommend Project A since its NPV is higher by $ 6885 than B ( $ 9169.75-$ 2283.99)


Related Solutions

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,700 ​$12,700 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$880 ​$1,530 Most likely 1,680 1,680 Optimistic 2,470 1,710 a. Determine the range of annual...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash inflows...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​12,200 ​12,200 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$800 ​$1,560 Most likely 1,700 1,700 Optimistic 2,480 1,720 a. Determine the range of...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,800 ​$12,800 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$860 ​$1,530 Most likely 1,680 1,680 Optimistic 2,500 1,780 a. Determine the range of annual cash...
Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity.
Project AProject BInitial investment(CF0)$12,600$12,600OutcomeAnnual cash inflows(CF )Pessimistic$810$1,590Most likely1,6101,610Optimistic2,4901,770Basic scenario analysis  Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.a. Determine the range of annual cash inflows for each of the two projects.b. Assume that the firm's cost of capital is 9.5% and that both...
P12-4 (similar to) Basic scenario analysis   Prime Paints is in the process of evaluating two mutually...
P12-4 (similar to) Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment 12,500 12,500 ​(CF 0CF0​) Outcome Annual cash inflows ​(CF CF ​) Pessimistic ​$880 ​$1,550 Most likely 1,690 1,690 Optimistic 2,420 1,790 a. Determine...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT