In: Finance
Basic scenario analysis
Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.
Initial investment
(CF0) |
$12,900 |
$12,900 |
Outcome |
Annual cash inflows
(CF ) |
|
Pessimistic |
$870 |
$1,530 |
Most likely |
1,690 |
1,690 |
Optimistic |
2,500 |
1 720 |
a. Determine the range of annual cash inflows for each of the two projects.
b. Assume that the firm's cost of capital is 9.2 % and that both projects have 19-year lives. Construct a table showing the NPVs for each project for each of the possible outcomes. Include the range of NPVs for each project
. c. Do parts (a) and (b) provide consistent views of the two projects? Explain. d. Which project do you recommend? Why?
A.The Range of Annual cash flow
For Project A- $ 870- $ 2500
For Project B - $ 1530 - $ 1720
B.
Calculation of discounted cash flows for each possible outcome of the project |
Project A | Project B | |||||
Particulars | Amount ( $) | Present value factor of Annuity @ 9.2% | Discounted Cash Flows | Amount ( $) | Present value factor of Annuity @ 9.2% | Discounted Cash Flows |
1 | 2 | 3 | 4(2*3) | 5 | 6 | 7(5*6) |
Pesimistic | $870 | 8.8279 | $7,680.27 | $1,530 | 8.8279 | $13,506.69 |
Most likely | $1,690 | 8.8279 | $14,919.15 | $1,690 | 8.8279 | $14,919.15 |
Optimistic | $2,500 | 8.8279 | $22,069.75 | $1,720 | 8.8279 | $15,183.99 |
B.Calculation of Net present value for each possible outcome of the project.
Project A | Project - B | |||||
Particulars | Pesimistic | Most likely | Optimistic | Pesimistic | Most likely | Optimistic |
A.Total income genereated from the project ( Step 1) | $7,680.27 | $14,919.15 | $22,069.75 | $13,506.69 | $14,919.15 | $15,183.99 |
B.Initial outlay of the Project | $12,900 | $12,900 | $12,900 | $12,900 | $12,900 | $12,900 |
C.Net Present Value | ($5,219.73) | $2,019.15 | $9,169.75 | $606.69 | $2,019.15 | $2,283.99 |
NPV Range for Project A - ( $ 5219.73) To $ 9169.7
Project B - $ 606.69 To $ 2283.99
C.If the outcome is in the point of view of Pessimistic then the project A is not at all viable,because the project will lead to as end up of Negative NPV of $5219.73.In case of Project B , even in case of pessimestic view also the projects ends up with a positive NPV of $ 606.69. In case the outcome islikely we can accept any project since both are giving an positive outcommf poe of $ 2019.15. In case optimistic outcome project A is more viable since taking up this project involve higher positive NPV than B.
D.I would recommend project B because irrespective of the outcome,the result end up in a positive NPV.
In case of investor is risk averse and highly possessing a optmistic outcome than i would recommend Project A since its NPV is higher by $ 6885 than B ( $ 9169.75-$ 2283.99)