Question

In: Finance

​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...

​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows:

YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW
0 -105,000 -105,000
1 40,000 0
2 40,000 0
3 40,000 0
4 40,000 0
5 40,000 240,000

If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project b?

Solutions

Expert Solution


Related Solutions

​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(110,000​) ​$(110,000​) 1    40,000            0 2    40,000            0 3    40,000            0 4    40,000            0 5    40,000   240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? The NPV of Project A is ​$_____. The NPV of Project A is ​$_____. Which would be chosen...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 ------------- -100,000 ---------------   -100,000 1 --------------- 33,000 --------------- 0 2 --------------- 33,000 --------------- 0 3 --------------- 33,000 --------------- 0 4 --------------- 33,000 --------------- 0 5 --------------- 33,000 --------------- 210,000 If the appropriate discount rate on these projects is 12 percent, which would be chosen and why? 1. What is the NPV of...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR      PROJECT A CASH FLOW                 PROJECT B CASH FLOW    0          -110,000                                               -110,000    1          30,000                                                   0    2          30,000                                                   0    3          30,000                                                   0    4          30,000                                                   0    5          30,000                                                   210,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? What is the NPV...
 You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
 You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(102,000​) ​$(102,000) 1 32,000            00 2    32,000            00 3    32,000            00 4    32,000            00 5    32,000   230, 000 If the appropriate discount rate on these projects is 88 ​percent, which would be chosen and​ why? The NPV of Project A is
You have two mutually exclusive projects A and B and have constructed the NPV profiles for...
You have two mutually exclusive projects A and B and have constructed the NPV profiles for these projects. You find that the IRR of A is greater than the IRR of B but at an 8% cost of capital using the NPV method you would prefer project B. What is causing the NPV profile pattern that you are observing? Which project do you prefer and why? Essentially you are preferring one method over another so you need to discuss the...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
The large furniture retailer “Sofa So Good” is evaluating two mutually exclusive projects:        NPV versus...
The large furniture retailer “Sofa So Good” is evaluating two mutually exclusive projects:        NPV versus IRR. Consider the following projects, where the firms may only choose one not both:               The firm’s cost of capital/required return equals 9%        PLEASE NOTE: The firm’s cost of capital, K, acts as a hurdle rate, and is based on the costs involved in financing other firm projects. The Cost of capital allows us to decide to accept or reject an investment,...
You are considering two mutually exclusive projects. The NPV for project one is positive and higher...
You are considering two mutually exclusive projects. The NPV for project one is positive and higher than the NPV for project two, while the IRR for project two is higher than that for project one. Which project should the firm accept and why?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT