Question

In: Finance

Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity.




Project A

Project B

Initial investment

(CF0)

$12,600

$12,600

Outcome

Annual cash inflows

(CF )

Pessimistic

$810

$1,590

Most likely

1,610

1,610

Optimistic

2,490

1,770

Basic scenario analysis  

Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.

a. Determine the range of annual cash inflows for each of the two projects.

b. Assume that the firm's cost of capital is 9.5% and that both projects have 17-year lives. Construct a table showing the NPVs for each project for each of the possible outcomes. Include the range of NPVs for each project.

c. Do parts (a) and (b) provide consistent views of the two projects? Explain.

d. Which project do you recommend? Why?

a. The range of annual cash inflows for project A is $nothing.(Round to the nearest dollar.)

Solutions

Expert Solution

a)

Range refers to the difference between the highest and lowest values of the outcomes

  • Project A

Range of annual casflows = 2490 - 810 = $1680

  • Project B

Range of annual casflows = 1770 - 1590 = $180

b)

Net present value (NPV) = Present value of cash flows - Initial investment

Present value of cash flows = CF *(1+ (1 / (1+r)^n) ) / r

CF = Cash flow

r = cost of capital = 9.5%

n = number of years = 17

Scenerios PV of Cash flows (Project A) PV of Cash flows (Project B)
Pessimistic

810 *(1+ (1 / (1+0.095)^17) ) / 0.095

= 6703.59

1590*(1+ (1 / (1+0.095)^17) ) / 0.095

= 13158.89

Most likely

1610*(1+ (1 / (1+0.095)^17) ) / 0.095

=13324.42

1610*(1+ (1 / (1+0.095)^17) ) / 0.095

=13324.42

Optimistic

2490*(1+ (1 / (1+0.095)^17) ) / 0.095

=20607

1770*(1+ (1 / (1+0.095)^17) ) / 0.095

= 14648.58

Scenerios NPV (Project A) NPV (Project B)
Pessimistic = 6703.59 - 12600 = -5896 = 13158.89-12600= 558.89
Most likely = 13324.42-12600= 724.42 = 13324.42-12600= 724.22
Optimistic = 20607-12600= 8007 =14648.58-12600= 2048.58

Range pf NPV

Project A Project B
= 8007 -(-5896) = 13903

=2048.58 - 558.89 = 1489.69

c)

As shown by both a and b Project A has higher range than Project B . Project A is tend to perform worst in pessimistic situation , while it will perform best in an optimistic situation.

d)

If i am risk averse manager i will go for project B as it is providing positive NPV in all 3 scenerios . But a manager who is willing to take risk will choose Project A.


Related Solutions

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,700 ​$12,700 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$880 ​$1,530 Most likely 1,680 1,680 Optimistic 2,470 1,710 a. Determine the range of annual...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash inflows...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​12,200 ​12,200 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$800 ​$1,560 Most likely 1,700 1,700 Optimistic 2,480 1,720 a. Determine the range of...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​ $12,900    ​ $12,900    Outcome Annual cash inflows ​(CF ​) Pessimistic ​$870 ​$1,530 Most likely 1,690 1,690 Optimistic 2,500 1 720 a. Determine...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,800 ​$12,800 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$860 ​$1,530 Most likely 1,680 1,680 Optimistic 2,500 1,780 a. Determine the range of annual cash...
P12-4 (similar to) Basic scenario analysis   Prime Paints is in the process of evaluating two mutually...
P12-4 (similar to) Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment 12,500 12,500 ​(CF 0CF0​) Outcome Annual cash inflows ​(CF CF ​) Pessimistic ​$880 ​$1,550 Most likely 1,690 1,690 Optimistic 2,420 1,790 a. Determine...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT