Question

In: Finance

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.

Project A

Project B

Initial investment

​(CF0​)

​$12,400

​$12,400

Outcome

Annual cash inflows

​(CF ​)

Pessimistic

​$840

​$1,560

Most likely

1,650

1,650

Optimistic

2,450

1,740

a. Determine the range of annual cash inflows for each of the two projects.

b. Assume that the​ firm's cost of capital is 9.2% and that both projects have 19​-year lives. Construct a table showing the NPVs for each project for each of the possible outcomes. Include the range of NPVs for each project.c. Do parts ​(a​) and ​(b​) provide consistent views of the two​ projects? Explain.

d. Which project do you​ recommend? Why?

a. The range of annual cash inflows for project A is​$16101610.

​(Round to the nearest​ dollar.)The range of annual cash inflows for project B is $180180.

​ (Round to the nearest​ dollar.)b. Assume that the​ firm's cost of capital is 9.2% and that both projects have 19​-year lives. Complete the NPV table below for project​ A:  ​(Round to the nearest​ cent.)

NPVs

Outcome

Project A

Pessimistic

$

Most likely

2,166.00

Optimistic

Range

$

Solutions

Expert Solution

b)

Project A Project B
Initial cost -12400 -12400
Pessimistic Annual CF 840 1560
NPV -$4,984.55 $1,371.54
Most likely Annual CF 1650 1650
NPV $2,166.05 $2,166.05
Optimistic Annual CF 2450 1740
NPV $9,228.38 $2,960.57
Range of NPV $14,212.94 $1,589.02

c) Parts ​(a​) and ​(b​) provide consistent views of the two​ projects since the Range of cash flows is higher in Project A and range of NPV is also higher in Project A. This represents variability in cash flows which presents higher risk in this project.

d) I recommend Project B since the risk is lesser and the NPV is positive in all cases.

WORKINGS


Related Solutions

Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,700 ​$12,700 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$880 ​$1,530 Most likely 1,680 1,680 Optimistic 2,470 1,710 a. Determine the range of annual...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​12,200 ​12,200 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$800 ​$1,560 Most likely 1,700 1,700 Optimistic 2,480 1,720 a. Determine the range of...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​ $12,900    ​ $12,900    Outcome Annual cash inflows ​(CF ​) Pessimistic ​$870 ​$1,530 Most likely 1,690 1,690 Optimistic 2,500 1 720 a. Determine...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,800 ​$12,800 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$860 ​$1,530 Most likely 1,680 1,680 Optimistic 2,500 1,780 a. Determine the range of annual cash...
Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity.
Project AProject BInitial investment(CF0)$12,600$12,600OutcomeAnnual cash inflows(CF )Pessimistic$810$1,590Most likely1,6101,610Optimistic2,4901,770Basic scenario analysis  Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table.a. Determine the range of annual cash inflows for each of the two projects.b. Assume that the firm's cost of capital is 9.5% and that both...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT