Question

In: Operations Management

2. Consider a project having the following seven activities:                                 &

2. Consider a project having the following seven activities:

                                                  Normal      Normal      Crash         Crash         Maximum

                        Immediate         Time        Cost         Time         Cost             Weeks

      Activity     Predecessors     (weeks)         ($)         (weeks)         ($)         Reduced

            A              none                  4            3,000            3            6,000               1

            B              none                  3            5,000            2            7,000               1

            C              A                    9            2,000            7            4,000               2

            D              A, B                  2            3,000            2            3,000               0

            E              B                     9            4,000            6            7,000               3

            F              C, D                  8            4,000            6            9,000               2

            G              E, F                   5            2,000            3            5,000               2

(a) What is the expected project completion time?   (3pts)

(b) What is the critical path?                                      (3pts

(c) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks?     (4pts)

Solutions

Expert Solution

activity required time cost time available for crashing= normal duration-crashed duration cost of crashing per period= (crashing cost-normal cost)/periods available for crashing
normal duration crashed duration normal cost crashing cost
a 4 3                 3,000               6,000 1 $3,000
b 3 2                 5,000               7,000 1 $2,000
c 9 7                 2,000               4,000 2 $1,000
d 2 2                 3,000               3,000 0 -
e 9 6                 4,000               7,000 3 $1,000
f 8 6                 4,000               9,000 2 $2,500
g 5 3                 2,000               5,000 2 $1,500
PATH normal duration
bdfg 18
adfg 19
acfg 26
beg 17

a: Expect completion time through the critical path is 26 weeks

b: critical path is A-C-F-G

c:

Steps for crashing a project
1 select the critical path and find the process with the least cost of crashing per week
2 If there are multiple critical paths, look for processes that are common, common processes may have low effective cost as common process crashes more than 1 path at once
3 you can only crash an activity depending on the time available for crashing. If an activity is only crashed that much time, choose another activity
4 add the cost of crashing later

Crashing

PATH normal duration crash C by 2 periods crash G by 1 period
bdfg 18 18 17
adfg 19 19 18
acfg 26 24 23
beg 17 17 16
Cost $23,000 $1,000 $1,500

it will cost $2500 to crash by 3 weeks.


Related Solutions

1. Consider a project having the following seven activities:                                 &
1. Consider a project having the following seven activities:                                                                         Optimistic        Most likely      Pessimistic                                           Immediate              Time (o)          Time (m)         Time (p)             Activity                 Predecessors         (weeks)           (weeks)           (weeks)                   A                     none                            4                      7                      9                   B                     none                            3                      5                      8                   C                     A                               2                      4                      6                   D                     A, B                            6                      9                      9                   E                      C, D                            5                      5                      5                   F                      B                               2                      5                      9                   G                     E, F                             3                      3                      6 (a) What is the expected time for...
Consider a project having the following activities, time, and cost:                                
Consider a project having the following activities, time, and cost:                                                   Normal      Normal      Crash         Crash         Maximum                         Immediate         Time        Cost         Time         Cost             Time       Activity      Predecessors      (weeks)          ($)         (weeks)          ($)         Reduced             a               none                  4            3,000            2            5,000               2             b               a                        5            5,000            3            8,000               2             c               a                        4            7,000            4            7,000               0             d               b                       4            6,000            2            8,000               2             e               c,d                     8            4,000            6            8,000               2             f               c                        3           ...
3. Consider a project having the following activities, time, and cost:                               &nb
3. Consider a project having the following activities, time, and cost:                                                   Normal       Normal       Crash         Crash      Maximum                         Immediate          Time         Cost         Time          Cost         Time       Activity      Predecessors      (weeks)          ($)          (weeks)          ($)       Reduced             a               none                  4            3,000             2            5,000            2             b               a                        5            5,000             3            8,000            2             c               a                        4            7,000             4            7,000            0             d               b                        4            6,000             2            8,000            2             e               c,d                     8            4,000             6            8,000            2             f               c                       ...
Question 2: Consider the following activities and their durations and requirements for a construction project. Activity...
Question 2: Consider the following activities and their durations and requirements for a construction project. Activity Predecessors Activity Duration (days) Optimistic Most likely Pessimistic A - 2 7 9 B - 3 6 9 C - 3 5 8 D A 15 19 20 E B, C 6 9 10 F C 2 4 6 G A, E 4 8 13 H G 1 2 4 Part a) Draw the project network and determine the critical path in the project...
Consider the following network of a project consisting of 7 activities with a scheduled project duration...
Consider the following network of a project consisting of 7 activities with a scheduled project duration of 36 weeks. Direct cost $12,000 with 36 weeks Indirect cost of $ 150 per week and delay damages of $ 500 per week for project duration beyond 30 weeks, and no incentive plan. the following table of time-cost data. Suppose the project should be completed in 30 weeks, what is the total project cost? Activity Predecessor. Normal Time (weeks) Crash Time (weeks) Normal...
Consider a project consisting of four activities A, B, C, and D. The following are constraints...
Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted • A and B, the first activities of the project, can be started simultaneously. • C can be started only after A is completed. • D can be started only after B is completed Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D =...
Problem #2 PERT Analysis: The following represents a project with four activities. All times are in...
Problem #2 PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 9 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in...
Consider the following project:
Consider the following project:                                Y0         Y1       Y2         Y3         Y4        Y5         Y6         Y7 CF                            $0    –$100   $50        $80     $30       $30       $30     –$60 a) What is the IRR? b) What is the payback time?
Consider the following activity-on-arc project network, wherethe 12 arcs (arrows) represent the 12 activities (tasks)...
Consider the following activity-on-arc project network, where the 12 arcs (arrows) represent the 12 activities (tasks) that must be performed to complete the project and the network displays the order in which the activities need to be performed. The number next to each arc (arrow) is the time required for the corresponding activity. Consider the problem of finding the longest path (the largest total time) through this network from start (node 1) to finish (node 9), since the longest path...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT