Question

In: Operations Management

Consider a project consisting of four activities A, B, C, and D. The following are constraints...

Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted

• A and B, the first activities of the project, can be started simultaneously.

• C can be started only after A is completed.

• D can be started only after B is completed

Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D = 3 weeks.

1. How long does the project take to complete?

2. We ask the engineers working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineers tell us that activity A takes 2 weeks 25% of the time, 4 weeks 50% of the time and 6 weeks 25% of the time. How long does the project now take to complete (on average)?

3. Suppose the project manager wants to be 60% certain that the project would be completed? What is deadline should they commit to?

4. We now also ask the engineer working on activity B to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineer now tell us that activity B takes 2 weeks 25% of the time, and 3 weeks 50% of the time and 4 weeks 25% of the time time. How long does the project now take to complete (on average)? [ASSUME THAT BOTH ACTIVITY A AND ACTIVITY B ARE UNCERTAIN]

5. For this scenario, what deadline should they commit to that would ensure a 60% probability of completion?

Solutions

Expert Solution

1). A=4 weeks, B=3 weeks, C=2 weeks, D=3 weeks

Assuming A & B start simultaneously, C starts after A and D starts after B

A + C=6 weeks

B + D=6 weeks

Hence all 4 activities are completed in 6 weeks

2). Using the uncertainity probabilities,

when A takes 2 weeks, A+C=4 weeks & B+D=6 weeks, so the project will take 6 weeks(when all activities are done)

when A takes 4 weeks, the project will take 6 weeks (as in problem 1)

when A takes 6 weeks, A+C=8 weeks & B+D=6 weeks, so the project will take 8 weeks

Applying the probabilities, Avg. completion time= 6*.25 + 6*.5 +8*.25 = 6.5 weeks

3). For 60% certainity, the deadlines of 6 weeks from the above problem will combine to give a 75% probability of work completion, which will satisfy the 60% criteria. Hence they should commit to 6 weeks.

4). Considering A+C is one activity, and B+D is another (since these 2 sums determine the project completion)

when B=2 weeks, B+D=5 weeks

when B=3 weeks, B+D=6 weeks

when B=4 weeks, B+D=7 weeks

Now both A and B are uncertain activities, so we have 9 combinations of competion times. In each combination, the task taking longer time is the defining component. And each completion time will be multiplies with respective probabilities of A and B.

For example, when A+B=5 and B+D=4, completion time=5 & probability =.25*.25

when A+B=5 anad B+D=6, completion time=6 & probability =.25*.5

Similarly all probabilities can be completed

So Average completion time = (5*.25*.25+6*.25*.5+....) = 6.625 weeks

5). For 60% probability, we just need to start adding up the probabilties from the shortest project completion times.

P(5 weeks)= .25*.25= .0625

P(6 weeks)= .25*.5 + .25*.5 + .5*.5 = .5

so the total probabiltiy is still less than 6 weeks

Adding the 7 weeks probability as well, it would become .75, which would fulfill the 60% criteris

Hence they should commit for 7 weeks


Related Solutions

A project has four activities (A, B, C, and D) that must be performed sequentially. The...
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.32 6 0.39 7 0.27 8 0.02 B 4 0.18 6 0.51 8 0.31 C 7 0.10 9 0.29 11 0.43 13 0.15 15 0.03 D 10 0.61 12 0.39 Provide the base-case, worst-case, and best-case calculations for the time to complete...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 3 0.29 4 0.38 5 0.29 6 0.04 B 7 0.22 9 0.53 11 0.25 C 9 0.05 11 0.24 13 0.36 15 0.19 17 0.16 D 10 0.59 12 0.41 Provide the base-case, worst-case, and best-case calculations for the...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
A family consisting of four persons—A, B, C, and D—belongs to a medical clinic that always...
A family consisting of four persons—A, B, C, and D—belongs to a medical clinic that always has a doctor at each of stations 1, 2, and 3. During a certain week, each member of the family visits the clinic once and is assigned at random to a station. The experiment consists of recording the station number for each member. Suppose that any incoming individual is equally likely to be assigned to any of the three stations irrespective of where other...
A project has five activities: A, B, C, and D, which must be carried out sequentially....
A project has five activities: A, B, C, and D, which must be carried out sequentially. The probability distributions of the number of weeks required to complete each of the activities A, B, and C are uniform in intervals [1,5], [2,3], and [3,6], respectively. The number of weeks required to complete activity D is a beta distribution with shape parameters a=2 and b=5, lower bound 2, and upper bound 10. Use simulation to forecast the total completion time of the...
We consider a GSP auction with four bidders, A, B, C and D. Since there are...
We consider a GSP auction with four bidders, A, B, C and D. Since there are four bidders only the three highest bidders will be displayed). The click frequency of the first, second and third positions are 100 clicks/hour, 75 clicks/hour and 35 clicks/hour, respectively. Bidders’valuation per click are vA = 10, vB = 6, vC = 4, vD = 3. Bidder B, C and D bid 5, 3 and 1, respectively. What is the optimal bid for A?
Consider the cross: A/a; b/b; C/c; D/d; E/e x A/a; B/b; c/c; D/d; e/e a) what...
Consider the cross: A/a; b/b; C/c; D/d; E/e x A/a; B/b; c/c; D/d; e/e a) what proportion of the progeny will phenotypically resemble the first parent? b) what proportion of the progeny will genotypically resemble neither parent?
MIPS a) Consider the C statement: a = (b + d) + (b - c) +...
MIPS a) Consider the C statement: a = (b + d) + (b - c) + (c + d) Which of the following assembly instructions can be used to replicate all or part of this statement in MIPS, without changing or reducing the equation. Assume variables a, b, c, and d are assigned to registers $s0, $s1, $s2 and $s3 respectively. 1. sub $t0, $s2, $s3 2. sub $t0, $s0, $s3 3. sub $t1, $s1, $s2 4. sub $t2, $s1,...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
Consider an experiment with four independent variables: A, B, C, and D. Factor A has 3...
Consider an experiment with four independent variables: A, B, C, and D. Factor A has 3 levels and is a between-subjects variable; Factor B has 2 levels and is a within-subjects variable; Factor C has 2 levels and is a between-subjects variable; Factor D has 3 levels and is a within-subjects variable. 1. How many “cells” or “conditions” or “groups” are there in this experiment? 2. If you want to test 10 participants per cell, how many TOTAL participants will...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT