Question

In: Operations Management

Consider the following network of a project consisting of 7 activities with a scheduled project duration...

Consider the following network of a project consisting of 7 activities with a scheduled project duration of 36 weeks. Direct cost $12,000 with 36 weeks Indirect cost of $ 150 per week and delay damages of $ 500 per week for project duration beyond 30 weeks, and no incentive plan. the following table of time-cost data. Suppose the project should be completed in 30 weeks, what is the total project cost?



Activity

Predecessor.

Normal Time (weeks)

Crash Time (weeks)

Normal cost ($)

Crash cost ($)

A

-

4

3

21,300

22,000

B

A

8

6

2,000

3,500

C

A

8

6

3,750

4,250

D

B,C

12

10

50,000

50,400

E

B,C

6

4

500

900

F

E

6

4

500

2,100

G

D,F

12

11

3,000

3,600




Solutions

Expert Solution

(Please like the answer it will encourage me. Do comment if any correction required before disliking.)


Related Solutions

Consider a project consisting of four activities A, B, C, and D. The following are constraints...
Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted • A and B, the first activities of the project, can be started simultaneously. • C can be started only after A is completed. • D can be started only after B is completed Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D =...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
Consider the following activity-on-arc project network, wherethe 12 arcs (arrows) represent the 12 activities (tasks)...
Consider the following activity-on-arc project network, where the 12 arcs (arrows) represent the 12 activities (tasks) that must be performed to complete the project and the network displays the order in which the activities need to be performed. The number next to each arc (arrow) is the time required for the corresponding activity. Consider the problem of finding the longest path (the largest total time) through this network from start (node 1) to finish (node 9), since the longest path...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities A 3 None B 5 None C 14 A D 5 A E 4 B F 7 B G 8 D, E H 5 G, F            (a)        Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path. [12 marks] (b)       Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks] (c)       From which activity...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
Consider a 10Mbps Ethernet network consisting of 20 nodes interconnected by a bus topology with a...
Consider a 10Mbps Ethernet network consisting of 20 nodes interconnected by a bus topology with a single bridge placed in the approximate centre of the network resulting in an equal number of nodes on each side of the bridge. a) Briefly explain why collisions can/cannot occur. b) If two pairs of nodes attempted to communicate at the same time, discuss the throughput they can achieve.
3. Consider a project having the following activities, time, and cost:                               &nb
3. Consider a project having the following activities, time, and cost:                                                   Normal       Normal       Crash         Crash      Maximum                         Immediate          Time         Cost         Time          Cost         Time       Activity      Predecessors      (weeks)          ($)          (weeks)          ($)       Reduced             a               none                  4            3,000             2            5,000            2             b               a                        5            5,000             3            8,000            2             c               a                        4            7,000             4            7,000            0             d               b                        4            6,000             2            8,000            2             e               c,d                     8            4,000             6            8,000            2             f               c                       ...