3. Consider a project having the following activities, time, and
cost:
Normal
Normal
Crash
Crash Maximum
Immediate
Time
Cost
Time
Cost Time
Activity
Predecessors
(weeks) ($)
(weeks) ($)
Reduced
a
none
4
3,000
2
5,000
2
b
a
5
5,000
3
8,000
2
c
a
4
7,000
4
7,000
0
d
b
4
6,000
2
8,000
2
e
c,d
8
4,000
6
8,000
2
f
c ...