Question

In: Operations Management

1. Consider a project having the following seven activities:                                 &

1. Consider a project having the following seven activities:

                                                                        Optimistic        Most likely      Pessimistic

                                          Immediate              Time (o)          Time (m)         Time (p)

            Activity                 Predecessors         (weeks)           (weeks)           (weeks)

                  A                     none                            4                      7                      9

                  B                     none                            3                      5                      8

                  C                     A                               2                      4                      6

                  D                     A, B                            6                      9                      9

                  E                      C, D                            5                      5                      5

                  F                      B                               2                      5                      9

                  G                     E, F                             3                      3                      6

(a) What is the expected time for each activity?

(b) What is the expected project completion time?

(c) What is the critical path?

(d) What are the expected time and variance of each path?

(e) What is the probability that the project will be completed in less than 22 weeks?

Solutions

Expert Solution

EXPECTED TIME = (OPTIMISTIC TIME + (4 * MOST LIKELY TIME) + PESSIMISTIC TIME) / 6

VARIANCE = ((PESSIMISTIC TIME - OPTIMISTIC TIME) / 6)^2


ACTIVITY

EXPECTED TIME

VARIANCE

A

(4 + (4 * 7) + 9) / 6 = 6.83

((9 - 4) / 6)^2 = 0.6944

B

(3 + (4 * 5) + 8) / 6 = 5.17

((8 - 3) / 6)^2 = 0.6944

C

(2 + (4 * 4) + 6) / 6 = 4

((6 - 2) / 6)^2 = 0.4444

D

(6 + (4 * 9) + 9) / 6 = 8.5

((9 - 6) / 6)^2 = 0.25

E

(5 + (4 * 5) + 5) / 6 = 5

((5 - 5) / 6)^2 = 0

F

(2 + (4 * 5) + 9) / 6 = 5.17

((9 - 2) / 6)^2 = 1.3611

G

(3 + (4 * 3) + 6) / 6 = 3.5

((6 - 3) / 6)^2 = 0.25


CPM


ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

6.83

0

6.83

0

6.83

0

B

5.17

0

5.17

1.66

6.83

1.66

C

4

6.83

10.83

11.33

15.33

4.5

D

8.5

6.83

15.33

6.83

15.33

0

E

5

15.33

20.33

15.33

20.33

0

F

5.17

5.17

10.34

15.16

20.33

9.99

G

3.5

20.33

23.83

20.33

23.83

0

FORWARD PASS: ES = MAXIMUM EF OF ALL PREDECESSOR ACTIVITIES; 0 IF NO PREDECESSORS ARE PRESENT. EF = ES + DURATION OF THE ACTIVITY.

BACKWARD PASS: LF = MINIMUM LS OF ALL SUCCESSOR ACTIVITIES; COMPLETION TIME OF THE PROJECT IF NO SUCCESSORS ARE PRESENT. LS = LF - DURATION OF THE ACTIVITY.

SLACK = LF - EF, OR, LS - ES

CRITICAL PATH = PATH WITH THE LONGEST COMBINED DURATION VALUE AND 0 SLACK.

CRITICAL PATH = A-D-E-G

DURATION OF PROJECT = 23.83


PROBABILITY

VARIANCE = 0.6944 + .25 + 0 + 0.25 = 1.1944

STANDARD DEVIATION = SQRT(VARIANCE) = SQRT(1.1944) = 1.092886

EXPECTED TIME = 23.83

DUE TIME = 22

Z = (DUE TIME - EXPECTED TIME) / STANDARD DEVIATION OF CRITICAL PATH)

Z = (22 - 23.83) / 1.092886 = -1.67

PROBABILITY FOR A Z VALUE OF -1.67 = NORMSDIST(-1.67) = 0.0475



Related Solutions

2. Consider a project having the following seven activities:                                 &
2. Consider a project having the following seven activities:                                                   Normal      Normal      Crash         Crash         Maximum                         Immediate         Time        Cost         Time         Cost             Weeks       Activity     Predecessors     (weeks)         ($)         (weeks)         ($)         Reduced             A              none                  4            3,000            3            6,000               1             B              none                  3            5,000            2            7,000               1             C              A                    9            2,000            7            4,000               2             D              A, B                  2            3,000            2            3,000               0             E              B                     9            4,000            6            7,000               3             F              C,...
Consider a project having the following activities, time, and cost:                                
Consider a project having the following activities, time, and cost:                                                   Normal      Normal      Crash         Crash         Maximum                         Immediate         Time        Cost         Time         Cost             Time       Activity      Predecessors      (weeks)          ($)         (weeks)          ($)         Reduced             a               none                  4            3,000            2            5,000               2             b               a                        5            5,000            3            8,000               2             c               a                        4            7,000            4            7,000               0             d               b                       4            6,000            2            8,000               2             e               c,d                     8            4,000            6            8,000               2             f               c                        3           ...
3. Consider a project having the following activities, time, and cost:                               &nb
3. Consider a project having the following activities, time, and cost:                                                   Normal       Normal       Crash         Crash      Maximum                         Immediate          Time         Cost         Time          Cost         Time       Activity      Predecessors      (weeks)          ($)          (weeks)          ($)       Reduced             a               none                  4            3,000             2            5,000            2             b               a                        5            5,000             3            8,000            2             c               a                        4            7,000             4            7,000            0             d               b                        4            6,000             2            8,000            2             e               c,d                     8            4,000             6            8,000            2             f               c                       ...
Consider the following network of a project consisting of 7 activities with a scheduled project duration...
Consider the following network of a project consisting of 7 activities with a scheduled project duration of 36 weeks. Direct cost $12,000 with 36 weeks Indirect cost of $ 150 per week and delay damages of $ 500 per week for project duration beyond 30 weeks, and no incentive plan. the following table of time-cost data. Suppose the project should be completed in 30 weeks, what is the total project cost? Activity Predecessor. Normal Time (weeks) Crash Time (weeks) Normal...
Consider a project consisting of four activities A, B, C, and D. The following are constraints...
Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted • A and B, the first activities of the project, can be started simultaneously. • C can be started only after A is completed. • D can be started only after B is completed Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D =...
Question 2: Consider the following activities and their durations and requirements for a construction project. Activity...
Question 2: Consider the following activities and their durations and requirements for a construction project. Activity Predecessors Activity Duration (days) Optimistic Most likely Pessimistic A - 2 7 9 B - 3 6 9 C - 3 5 8 D A 15 19 20 E B, C 6 9 10 F C 2 4 6 G A, E 4 8 13 H G 1 2 4 Part a) Draw the project network and determine the critical path in the project...
Question 1 16 Marks Consider a project with the following cash flows: Consider a project with...
Question 1 16 Marks Consider a project with the following cash flows: Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1 -80,500 2 138,425 3 -105,455 4 30,030 Required: 1.1.Fill in the following table: Cost of Capital (%) Project NPV 0 5 10 15 20 25 30 35 50 1.2.Use the values developed in part (1.1) to draw an NPV profile for this project. 1.3.What is the IRR for this project? 1.4.Describe the conditions under...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1...
1. Consider the seven missteps mentioned in How to mess up your agile transformation in seven...
1. Consider the seven missteps mentioned in How to mess up your agile transformation in seven easy (mis)step. The concepts Handscomb discusses in each of the missteps do have much validity. Can you think of any modern day examples of firms and/or projects that have exhibited these pitfalls? In addition, what would you have done differently?
Consider the following project:
Consider the following project:                                Y0         Y1       Y2         Y3         Y4        Y5         Y6         Y7 CF                            $0    –$100   $50        $80     $30       $30       $30     –$60 a) What is the IRR? b) What is the payback time?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT