Question

In: Operations Management

3. Consider a project having the following activities, time, and cost:                               &nb

3. Consider a project having the following activities, time, and cost:

                                                  Normal       Normal       Crash         Crash      Maximum

                        Immediate          Time         Cost         Time          Cost         Time

      Activity      Predecessors      (weeks)          ($)          (weeks)          ($)       Reduced

            a               none                  4            3,000             2            5,000            2

            b               a                        5            5,000             3            8,000            2

            c               a                        4            7,000             4            7,000            0

            d               b                        4            6,000             2            8,000            2

            e               c,d                     8            4,000             6            8,000            2

            f               c                        3            4,000             2            9,000            1

            g               e,f                      4            2,000             2            7,000            2

Assume partial crashing (not all maximum crashing time has to be used) is available.

  1. Draw the network diagram. How long does project take using normal time?
  2. Which activities should be crashed to reduce the completion time of the project by two weeks? How much is the additional cost? Show all work.

Solutions

Expert Solution

We find the crash cost per day for each activity as shown below:

Based on the predecessor relationship and durations given, we prepare a project network diagram as shown below:

The above network diagram in the form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration

Similarly, LFT & LST are calculated during the backward pass.

There are multiple paths in the diagram:

a-b-d-e-g

a-c-e-g

a-c-f-g

Out of the above paths, path a-b-d-e-g is the longest path and has 0 slack. Hence, this is the critical path.

As seen from above, without crashing the earliest the project can be completed is 25 days

To reduce project duration, we have to crash activities on the critical path first.

As seen from the above table, we start with crashing activities with minimum crash cost per day to have a minimum cost impact.

Step-1: We crash activity "a" as it has the lowest crash cost. We crash A by 2 days which is the maximum possible. Additional cost = No. of days crashed * crash cost per day = 2*1000 = $2000

Hence, as seen from above, we have to crash activity "a" by 2 weeks with an additional cost of $2000

_______________________________________________________________________________________

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

Consider a project having the following activities, time, and cost:                                
Consider a project having the following activities, time, and cost:                                                   Normal      Normal      Crash         Crash         Maximum                         Immediate         Time        Cost         Time         Cost             Time       Activity      Predecessors      (weeks)          ($)         (weeks)          ($)         Reduced             a               none                  4            3,000            2            5,000               2             b               a                        5            5,000            3            8,000               2             c               a                        4            7,000            4            7,000               0             d               b                       4            6,000            2            8,000               2             e               c,d                     8            4,000            6            8,000               2             f               c                        3           ...
2. Consider a project having the following seven activities:                                 &
2. Consider a project having the following seven activities:                                                   Normal      Normal      Crash         Crash         Maximum                         Immediate         Time        Cost         Time         Cost             Weeks       Activity     Predecessors     (weeks)         ($)         (weeks)         ($)         Reduced             A              none                  4            3,000            3            6,000               1             B              none                  3            5,000            2            7,000               1             C              A                    9            2,000            7            4,000               2             D              A, B                  2            3,000            2            3,000               0             E              B                     9            4,000            6            7,000               3             F              C,...
1. Consider a project having the following seven activities:                                 &
1. Consider a project having the following seven activities:                                                                         Optimistic        Most likely      Pessimistic                                           Immediate              Time (o)          Time (m)         Time (p)             Activity                 Predecessors         (weeks)           (weeks)           (weeks)                   A                     none                            4                      7                      9                   B                     none                            3                      5                      8                   C                     A                               2                      4                      6                   D                     A, B                            6                      9                      9                   E                      C, D                            5                      5                      5                   F                      B                               2                      5                      9                   G                     E, F                             3                      3                      6 (a) What is the expected time for...
The following activities are for a graduation party. Buy Tableware                               &nb
The following activities are for a graduation party. Buy Tableware                                  Create Guest List                        Purchase Banner                                                                                                                  Order Food/Drink                              Decorate Venue                           Mail Invitations                                              Update RSVP                                    Buy Balloons                                 Organize the activities in a work breakdown structure using the final end product and work packages. Party Invitations Catering Decorations * * * * * * * * * Complete an Activity List and Predecessors Table Activity Number Activity Predecessor 1 2 3 4 5 6 7 8 Put the activities in sequence using a network diagram. Please note there...
Consider the following network of a project consisting of 7 activities with a scheduled project duration...
Consider the following network of a project consisting of 7 activities with a scheduled project duration of 36 weeks. Direct cost $12,000 with 36 weeks Indirect cost of $ 150 per week and delay damages of $ 500 per week for project duration beyond 30 weeks, and no incentive plan. the following table of time-cost data. Suppose the project should be completed in 30 weeks, what is the total project cost? Activity Predecessor. Normal Time (weeks) Crash Time (weeks) Normal...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost Immediate Predecessors A 3 $3,000 None B 4 $6,000 None C 2 $7,000 A D 5 $9,000 B E 3 $3,000 C F 6 $8,000 B,D Develop a budget for the 15 weeks of the project using ES times. The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor...
Question 3 [14] Consider the following prices and quantities: Price (per kg)                             &nb
Question 3 [14] Consider the following prices and quantities: Price (per kg)                                         Quantities produced            2010 2012 2015 2010 2012 2015 Beans 3.95 3.89 4.13 675 717 436 Onions 61.50 62.20 59.70 117 115 115 Carrots 34.80 35.40 38.90 77 74 82 1. Compute and interpret the Paasche’s Quantity Index number for the year 2012 with 2010 as the base year.                                                                                                           (7) 2. Compute and interpret the Laspeyres Price Index number for the year 2015 with 2012 as...
Consider a project consisting of four activities A, B, C, and D. The following are constraints...
Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted • A and B, the first activities of the project, can be started simultaneously. • C can be started only after A is completed. • D can be started only after B is completed Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D =...
Question 2: Consider the following activities and their durations and requirements for a construction project. Activity...
Question 2: Consider the following activities and their durations and requirements for a construction project. Activity Predecessors Activity Duration (days) Optimistic Most likely Pessimistic A - 2 7 9 B - 3 6 9 C - 3 5 8 D A 15 19 20 E B, C 6 9 10 F C 2 4 6 G A, E 4 8 13 H G 1 2 4 Part a) Draw the project network and determine the critical path in the project...
3. Consider a project with a 6-year life. The initial cost to set up the project...
3. Consider a project with a 6-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 6 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 57,000 units per year at a price of $167 each....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT