Question

In: Operations Management

3. Consider a project having the following activities, time, and cost:                               &nb

3. Consider a project having the following activities, time, and cost:

                                                  Normal       Normal       Crash         Crash      Maximum

                        Immediate          Time         Cost         Time          Cost         Time

      Activity      Predecessors      (weeks)          ($)          (weeks)          ($)       Reduced

            a               none                  4            3,000             2            5,000            2

            b               a                        5            5,000             3            8,000            2

            c               a                        4            7,000             4            7,000            0

            d               b                        4            6,000             2            8,000            2

            e               c,d                     8            4,000             6            8,000            2

            f               c                        3            4,000             2            9,000            1

            g               e,f                      4            2,000             2            7,000            2

Assume partial crashing (not all maximum crashing time has to be used) is available.

  1. Draw the network diagram. How long does project take using normal time?
  2. Which activities should be crashed to reduce the completion time of the project by two weeks? How much is the additional cost? Show all work.

Solutions

Expert Solution

We find the crash cost per day for each activity as shown below:

Based on the predecessor relationship and durations given, we prepare a project network diagram as shown below:

The above network diagram in the form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration

Similarly, LFT & LST are calculated during the backward pass.

There are multiple paths in the diagram:

a-b-d-e-g

a-c-e-g

a-c-f-g

Out of the above paths, path a-b-d-e-g is the longest path and has 0 slack. Hence, this is the critical path.

As seen from above, without crashing the earliest the project can be completed is 25 days

To reduce project duration, we have to crash activities on the critical path first.

As seen from the above table, we start with crashing activities with minimum crash cost per day to have a minimum cost impact.

Step-1: We crash activity "a" as it has the lowest crash cost. We crash A by 2 days which is the maximum possible. Additional cost = No. of days crashed * crash cost per day = 2*1000 = $2000

Hence, as seen from above, we have to crash activity "a" by 2 weeks with an additional cost of $2000

_______________________________________________________________________________________

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

The following activities are for a graduation party. Buy Tableware                               &nb
The following activities are for a graduation party. Buy Tableware                                  Create Guest List                        Purchase Banner                                                                                                                  Order Food/Drink                              Decorate Venue                           Mail Invitations                                              Update RSVP                                    Buy Balloons                                 Organize the activities in a work breakdown structure using the final end product and work packages. Party Invitations Catering Decorations * * * * * * * * * Complete an Activity List and Predecessors Table Activity Number Activity Predecessor 1 2 3 4 5 6 7 8 Put the activities in sequence using a network diagram. Please note there...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost Immediate Predecessors A 3 $3,000 None B 4 $6,000 None C 2 $7,000 A D 5 $9,000 B E 3 $3,000 C F 6 $8,000 B,D Develop a budget for the 15 weeks of the project using ES times. The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor...
Question 3 [14] Consider the following prices and quantities: Price (per kg)                             &nb
Question 3 [14] Consider the following prices and quantities: Price (per kg)                                         Quantities produced            2010 2012 2015 2010 2012 2015 Beans 3.95 3.89 4.13 675 717 436 Onions 61.50 62.20 59.70 117 115 115 Carrots 34.80 35.40 38.90 77 74 82 1. Compute and interpret the Paasche’s Quantity Index number for the year 2012 with 2010 as the base year.                                                                                                           (7) 2. Compute and interpret the Laspeyres Price Index number for the year 2015 with 2012 as...
Consider a project consisting of four activities A, B, C, and D. The following are constraints...
Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted • A and B, the first activities of the project, can be started simultaneously. • C can be started only after A is completed. • D can be started only after B is completed Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D =...
3. Consider a project with a 6-year life. The initial cost to set up the project...
3. Consider a project with a 6-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 6 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 57,000 units per year at a price of $167 each....
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
3.         Question 3                               &nb
3.         Question 3                                                                                                      [Total: 20 marks] Assume a futures contract with 8 months to maturity is employed to hedge a well-diversified portfolio over the next 6 months.  The contract size of one futures contract is $250 times the index (i.e. the futures on the index). The value of the S&P500 index is currently 1200. The current futures price is $1220. The value of the portfolio that you are hedging is $ 40 million. The Beta of the portfolio is 1.25. The risk-free rate...
Consider the following portfolio of four stocks: Security                                &nb
Consider the following portfolio of four stocks: Security                                                Weight                 Beta ABC                                        .167                        3.09 DEF                                        .25                          0.63 GHI                                        .233                        1.54 JKL                                          .35                          1.81 The 25 - year government of Canada bond has a yield of 2% The market risk premium is 5% What is the portfolio beta? What is the expected return of each security?
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT