Question

In: Operations Management

Question 2: Consider the following activities and their durations and requirements for a construction project. Activity...

Question 2: Consider the following activities and their durations and requirements for a construction project.

Activity

Predecessors

Activity Duration (days)

Optimistic

Most likely

Pessimistic

A

-

2

7

9

B

-

3

6

9

C

-

3

5

8

D

A

15

19

20

E

B, C

6

9

10

F

C

2

4

6

G

A, E

4

8

13

H

G

1

2

4

Part a) Draw the project network and determine the critical path in the project network using most likely activity durations. (Show the network, total flow of each activity, and critical path)

Part b) How many days activity F could be delayed its early start date without delaying the start date of other activities? (Explanations and calculations)

Part c) If company’s president wants to have a 95% chance of completing the project before July 30, when should the project began? (Explanations and calculations)

Solutions

Expert Solution

Answer:

Paths Duration Variance
AD 25.00 2.58
AGH 16.83
BEGH 25.00 5.00
CEGH 24.17
CF 9.17
Critical Path Duration (days) Variance, σ2 Standard Deviation, σ (=sqrt(variance))
BEGH * 25.00 5.00 2.236


* In case of multiple critical paths use the one with the largest variance largest variance



Answer b

Activity Preceding Activity Duration, D Early start, ES=Max of early finish of preceeding activities Early finish, EF = ES + D Activity Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF Critical activity name Critical activity, activities with 0 slack time
A 7 0.00 6.50 A 6.50 0.00 0.00 A YES
B 6 0.00 6.00 B 6.00 0.00 0.00 B YES
C 5 0.00 5.17 C 6.00 0.83 0.83
D 19 6.50 25.00 D 25.00 6.50 0.00 D YES
E 9 6.00 14.67 E 14.67 6.00 0.00 E YES
F 4 5.17 9.17 F 25.00 21.00 15.83
G 8 14.67 22.83 G 22.83 14.67 0.00 G YES
H 2 22.83 25.00 H 25.00 22.83 0.00 H


Activity F has a total slack of 15.83 days. So activity F could be delayed (by 15.83 days) at its early start date without delaying the start date of other activities

Answer c

Dear Student,
Please ask, if you have any doubts through the comment section. Do rate the answer.


Related Solutions

Consider the project with the listed activities. Normal durations and costs, as well as crash durations...
Consider the project with the listed activities. Normal durations and costs, as well as crash durations and costs are listed for each activity. Precedence relationships are implicitly given by the activity names (e.g., activity (1,2) is represented as an arc from node 1 to node 2).                                 Crash     Crash                                     Normal                 Normal Activity                 Time      Cost                                       Time                      Cost (1, 2)                      5              $41,000                                 8                              $29,000 (1, 3)                      2              $18,000                                 3                              $10,000 (2, 4)                      10           $50,000                                 12                           $46,000 (2, 5)                      4              $26,000                                 6                             ...
A construction project is broken down into the following 10 activities: Activity Immediate Pred Weeks A...
A construction project is broken down into the following 10 activities: Activity Immediate Pred Weeks A - 6 B A 3 C A 4 D A 2 E B, C 4 F C 3 G D 7 H E 3 I F, G 5 J H, I 7 Please draw the network. What is the critical path? How many weeks will it take to complete the project? How much slack does each of the activities have? QUESTION A: PLEASE DRAW...
2. Consider a project having the following seven activities:                                 &
2. Consider a project having the following seven activities:                                                   Normal      Normal      Crash         Crash         Maximum                         Immediate         Time        Cost         Time         Cost             Weeks       Activity     Predecessors     (weeks)         ($)         (weeks)         ($)         Reduced             A              none                  4            3,000            3            6,000               1             B              none                  3            5,000            2            7,000               1             C              A                    9            2,000            7            4,000               2             D              A, B                  2            3,000            2            3,000               0             E              B                     9            4,000            6            7,000               3             F              C,...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
Consider the following activity-on-arc project network, wherethe 12 arcs (arrows) represent the 12 activities (tasks)...
Consider the following activity-on-arc project network, where the 12 arcs (arrows) represent the 12 activities (tasks) that must be performed to complete the project and the network displays the order in which the activities need to be performed. The number next to each arc (arrow) is the time required for the corresponding activity. Consider the problem of finding the longest path (the largest total time) through this network from start (node 1) to finish (node 9), since the longest path...
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
1. Consider a project having the following seven activities:                                 &
1. Consider a project having the following seven activities:                                                                         Optimistic        Most likely      Pessimistic                                           Immediate              Time (o)          Time (m)         Time (p)             Activity                 Predecessors         (weeks)           (weeks)           (weeks)                   A                     none                            4                      7                      9                   B                     none                            3                      5                      8                   C                     A                               2                      4                      6                   D                     A, B                            6                      9                      9                   E                      C, D                            5                      5                      5                   F                      B                               2                      5                      9                   G                     E, F                             3                      3                      6 (a) What is the expected time for...
Consider a project having the following activities, time, and cost:                                
Consider a project having the following activities, time, and cost:                                                   Normal      Normal      Crash         Crash         Maximum                         Immediate         Time        Cost         Time         Cost             Time       Activity      Predecessors      (weeks)          ($)         (weeks)          ($)         Reduced             a               none                  4            3,000            2            5,000               2             b               a                        5            5,000            3            8,000               2             c               a                        4            7,000            4            7,000               0             d               b                       4            6,000            2            8,000               2             e               c,d                     8            4,000            6            8,000               2             f               c                        3           ...
Draw the PERT and Gantt (calendar) charts for the following list of activities and expected durations....
Draw the PERT and Gantt (calendar) charts for the following list of activities and expected durations. Identify the critical path and list the slack times (if any) for the activities. Activity Immediate Predecessor Duration A - 3 B - 3 C - 4 D A, B 5 E B, C 4 F D, E 2 G E 3 H F, G 5  