In: Operations Management
Draw the schedule network diagram using Precedence Diagramming Method (PDM) and calculate Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), and Latest Finish (LF) for each activity.
Activity |
Predecessor |
Duration |
A |
2 |
|
B |
3 |
|
C |
3 |
|
D |
A |
3 |
E |
D |
3 |
F |
E |
4 |
G |
F |
3 |
H |
F |
5 |
I |
G, H |
6 |
J |
G |
3 |
K |
H |
4 |
L |
I, K |
4 |
M |
J |
2 |
Based on the given data, we prepare AON diagram using Precedence Diagramming Method (PDM) as shown below
The
above network diagram in the form of formulas is shown below for
better understanding and reference:
The
above project diagram is prepared as per the legend shown in the
top-left corner.
EST = Early start time
LST = Late start time
EFT = Early finish time
LFT = Late finish time
SLK = Slack = LST - EST or Slack = LFT - EFT
The EST of an activity = EFT of previous activity
EFT of an activity = EST + Duration - 1
Similarly, LFT & LST are calculated during the backward pass. The activity END is only a dummy activity that is introduced for backward pass calculations only. It will not be considered for any other purpose.
Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), and Latest Finish (LF) for each activity is shown in each activity box as pe legend.
----------------------------------------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.