Question

In: Operations Management

Draw the schedule network diagram using Precedence Diagramming Method (PDM) and calculate Earliest Start (ES), Earliest...

Draw the schedule network diagram using Precedence Diagramming Method (PDM) and calculate Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), and Latest Finish (LF) for each activity.

Activity

Predecessor

Duration

A

2

B

3

C

3

D

A

3

E

D

3

F

E

4

G

F

3

H

F

5

I

G, H

6

J

G

3

K

H

4

L

I, K

4

M

J

2

Solutions

Expert Solution

Based on the given data, we prepare AON diagram using Precedence Diagramming Method (PDM) as shown below

The above network diagram in the form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration - 1

Similarly, LFT & LST are calculated during the backward pass. The activity END is only a dummy activity that is introduced for backward pass calculations only. It will not be considered for any other purpose.

Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), and Latest Finish (LF) for each activity is shown in each activity box as pe legend.

----------------------------------------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS,...
Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS, LF, TF and FF for each activity. Which activities in the project are on the critical path Activity Duration IPA Type of relationship Lag A 4 B 3 C 8 A D 7 A, B E 6 D SS 3 F 3 D G 5 F SS FF 2 Note: If the relationship type is not mentioned, it is FS. If no lag/lead is...
1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For...
1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For each activity, show the computed value of early start, early finish, late start, late finish, total float, and free float.   Activity Duration mobilize 1 remove siding 4 excavate/form slab 7 place slab 4 set support beam 1 stud wall up 6 install siding 4 install windows 5 set raffers 4 install roof 6 finish trim 4 paint siding 7 move out 1
In the Critical Path Method network diagram, what is unique about the early start and early...
In the Critical Path Method network diagram, what is unique about the early start and early finish date of each node on the critical path?
Question 1 a. Draw a precedence diagram for the following fabrication of steel project. For each...
Question 1 a. Draw a precedence diagram for the following fabrication of steel project. For each activity, show the computed values of early start, early finish, late start, late finish, total float, free float and the critical path. Activity Immediate Predecessor Duration (weeks) A None 2 B A 4 C A 2 D B 2 E B, C 4 F A, E 6 G D 4 H D, E, F 2 I G, H 6 J H, F 6 K...
Please design the network and draw the network diagram. You have the freedom to assume the...
Please design the network and draw the network diagram. You have the freedom to assume the internal network structure. In the diagram, in addition to the 2 servers, you should also include a few desktop computers and a printer. Please explain the rationale on why you put a computer or a printer in its designated location, 1 example for each location. A subnet (or a segment) is regarded as the same location. (hint: a firewall or a few firewalls, depending...
Can you draw a network diagram for this? In VISO would be an extra bonus There...
Can you draw a network diagram for this? In VISO would be an extra bonus There are two available rooms, named RH230 and RH231, in your building. You are asked to set up a server room in RH230 and a computer lab in RH231. Design a Local area network that satisfies the following conditions.  You have two 8-port switches.  Cables as you need.  Four server machines in RH230: Gateway server, DNS server, DHCP server, and Web server....
Activity network diagram is used to develop a work schedule for the facilities design effort. Activity...
Activity network diagram is used to develop a work schedule for the facilities design effort. Activity A to K is descried as follows: A with a duration of 2 month; B has immediate predecessor of A with total duration of 4 month; C has immediate predecessor of (A) with total duration of 2 month; (D) has immediate predecessor of B with total duration of 2month; (E) has immediate predecessor of B and C with total duration of 4 month; (F)...
Develop an iteration schedule diagram using the information provided in the attached document. Create this schedule...
Develop an iteration schedule diagram using the information provided in the attached document. Create this schedule using either Microsoft Project or ProjectLibre. Discipline Activity Effort Planning Set up work environment 2 days Develop WBS and plan work 1 day Analysis Activities Meet with Community Board users 2 days Meet with several agents 2 days Define data 1 day Model use cases 2 days Design Activities Design screen layouts 3 days Design Database 1 day Design use case processing 3 days...
Create a diagram of a Small/Medium size Business network Using Computer Network Defense and Defense in...
Create a diagram of a Small/Medium size Business network Using Computer Network Defense and Defense in Depth, Define what a secure network should look like on a modest budget. (Describe your diagram and why you placed your appliances where you chose to place them).
Using a cash flow diagram draw a diagram for $10,000 invested now, and in 5 years...
Using a cash flow diagram draw a diagram for $10,000 invested now, and in 5 years it grows to $30,000.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT