Activity network diagram is used to develop a work schedule for
the facilities design effort. Activity...
Activity network diagram is used to develop a work schedule for
the facilities design effort. Activity A to K is descried as
follows: A with a duration of 2 month; B has immediate predecessor
of A with total duration of 4 month; C has immediate predecessor of
(A) with total duration of 2 month; (D) has immediate predecessor
of B with total duration of 2month; (E) has immediate predecessor
of B and C with total duration of 4 month; (F) has immediate
predecessor of A and E with total duration of 6 month; (G) has
immediate predecessor of D with total duration of 4 month; (H) has
immediate predecessor of D, E, F with total duration of 2 month;
(I) has immediate predecessor of H, F with total duration of 6
month; (J ) has immediate predecessor of H and F with total
duration of 6 month, (K) has immediate predecessor of H, I, J with
total duration of 4 month. What is the project duration and the
critical activities?
28 months
and A, B, E, F, H, I, J, and K
28 months
and A, B, E, H, F, I, J, and K
27 months
and A, B, E, F, H, I, J, and K
27 months
and A, B, E, H, F, I, J, and K
Solutions
Expert Solution
here both i and j are part of critical path .hence it is
critical activity here both option A and B are same only.
Develop an iteration schedule diagram using the information
provided in the attached document. Create this schedule using
either Microsoft Project or ProjectLibre.
Discipline
Activity
Effort
Planning
Set up work environment
2 days
Develop WBS and plan work
1 day
Analysis Activities
Meet with Community Board users
2 days
Meet with several agents
2 days
Define data
1 day
Model use cases
2 days
Design Activities
Design screen layouts
3 days
Design Database
1 day
Design use case processing
3 days...
Please design the network and draw the network diagram. You have
the freedom to assume the internal network structure. In the
diagram, in addition to the 2 servers, you should also include a
few desktop computers and a printer. Please explain the rationale
on why you put a computer or a printer in its designated location,
1 example for each location. A subnet (or a segment) is regarded as
the same location. (hint: a firewall or a few firewalls, depending...
Activity 1 - Network Design Proposal
In this section, you are required to write a Network Design
Proposal. You will need to: 1. Describe the network design scenario
that needs to be addressed. 2. Provide a network design solution.
3. Write a complete network design proposal. 4. Develop (implement)
a highâlevel solution showing important components of the solution
using a virtualization tool.
Ex1) Develop an activity diagram and use case diagram based on
the following narrative. The purpose of the Open Access Insurance
System is to provide automotive insurance to car owners. Initially,
prospective customers fill out an insurance application, which
provides information about the customer and his or her vehicles.
This information is sent to an agent, who sends it to various
insurance companies to get quotes for insurance. When the responses
return, the agent then determines the best policy for...
1. Create a network diagram and project schedule
(illustrated in a Gantt chart) from the following set of tasks. Use
the task number, duration, and dependencies of each task given and
construct a schedule so that the project is completed in the least
number of days possible. Include a management reserve of
approximately 10%.
Task
Subject
Duration
Dependencies
Slack (3 pts)
1.0
Project Kickoff
2
none
2.1
Install & Test Database Software
2
1.0
2.2
Configure & Test Database Web...
Completely and thoroughly explain how Facilities Design could be
used to design a new facility for a company that makes clothing.
Discuss the issues of raw material deliveries at the receiving
dock, unloading trucks and storing the raw materials, movement of
raw materials to the manufacturing areas, monitoring and moving
work-in-process throughout the manufacturing area, delivering
finished goods to the warehouse, and consolidating customer orders
for shipment. Be sure to focus your discussion on a company that
makes clothing.
Write an application case study with network design diagram
including the following topics:
- IoT
- Bluetooth
- Fog Computing
- Redundant
- Resilient and measures of resilience
- Troubleshooting with half split and move method
Highlight in bold each of the above keywords.
Write an application case study with network design diagram
including the following topics: - IoT - Bluetooth - Fog Computing -
Redundant - Resilient and measures of resilience - Troubleshooting
with half split and move method Highlight in bold each of the above
keywords.
Draw the schedule network diagram using Precedence Diagramming
Method (PDM) and calculate Earliest Start (ES), Earliest Finish
(EF), Latest Start (LS), and Latest Finish (LF) for each
activity.
Activity
Predecessor
Duration
A
2
B
3
C
3
D
A
3
E
D
3
F
E
4
G
F
3
H
F
5
I
G, H
6
J
G
3
K
H
4
L
I, K
4
M
J
2