Question

In: Mechanical Engineering

Activity network diagram is used to develop a work schedule for the facilities design effort. Activity...

  1. Activity network diagram is used to develop a work schedule for the facilities design effort. Activity A to K is descried as follows: A with a duration of 2 month; B has immediate predecessor of A with total duration of 4 month; C has immediate predecessor of (A) with total duration of 2 month; (D) has immediate predecessor of B with total duration of 2month; (E) has immediate predecessor of B and C with total duration of 4 month; (F) has immediate predecessor of A and E with total duration of 6 month; (G) has immediate predecessor of D with total duration of 4 month; (H) has immediate predecessor of D, E, F with total duration of 2 month; (I) has immediate predecessor of H, F with total duration of 6 month; (J ) has immediate predecessor of H and F with total duration of 6 month, (K) has immediate predecessor of H, I, J with total duration of 4 month. What is the project duration and the critical activities?
  • 28 months
  • and A, B, E, F, H, I, J, and K
  • 28 months
  • and A, B, E, H, F, I, J, and K
  • 27 months
  • and A, B, E, F, H, I, J, and K
  • 27 months
  • and A, B, E, H, F, I, J, and K

Solutions

Expert Solution

here both i and j are part of critical path .hence it is critical activity here both option A and B are same only.

please don't forget to rate the answer.

you can clear doubts in comment section thank you


Related Solutions

Develop an iteration schedule diagram using the information provided in the attached document. Create this schedule...
Develop an iteration schedule diagram using the information provided in the attached document. Create this schedule using either Microsoft Project or ProjectLibre. Discipline Activity Effort Planning Set up work environment 2 days Develop WBS and plan work 1 day Analysis Activities Meet with Community Board users 2 days Meet with several agents 2 days Define data 1 day Model use cases 2 days Design Activities Design screen layouts 3 days Design Database 1 day Design use case processing 3 days...
Please design the network and draw the network diagram. You have the freedom to assume the...
Please design the network and draw the network diagram. You have the freedom to assume the internal network structure. In the diagram, in addition to the 2 servers, you should also include a few desktop computers and a printer. Please explain the rationale on why you put a computer or a printer in its designated location, 1 example for each location. A subnet (or a segment) is regarded as the same location. (hint: a firewall or a few firewalls, depending...
Ex1) Develop an activity diagram and use case diagram based on the following narrative. The purpose...
Ex1) Develop an activity diagram and use case diagram based on the following narrative. The purpose of the Open Access Insurance System is to provide automotive insurance to car owners. Initially, prospective customers fill out an insurance application, which provides information about the customer and his or her vehicles. This information is sent to an agent, who sends it to various insurance companies to get quotes for insurance. When the responses return, the agent then determines the best policy for...
Design a16-bit RISC MIPS Processor. Develop modules, a block diagram, Verilog codes used, and the waveforms...
Design a16-bit RISC MIPS Processor. Develop modules, a block diagram, Verilog codes used, and the waveforms screen-prints.
Completely and thoroughly explain how Facilities Design could be used to design a new facility for...
Completely and thoroughly explain how Facilities Design could be used to design a new facility for a company that makes clothing. Discuss the issues of raw material deliveries at the receiving dock, unloading trucks and storing the raw materials, movement of raw materials to the manufacturing areas, monitoring and moving work-in-process throughout the manufacturing area, delivering finished goods to the warehouse, and consolidating customer orders for shipment. Be sure to focus your discussion on a company that makes clothing.
Write an application case study with network design diagram including the following topics: - IoT -...
Write an application case study with network design diagram including the following topics: - IoT - Bluetooth - Fog Computing - Redundant - Resilient and measures of resilience - Troubleshooting with half split and move method Highlight in bold each of the above keywords.
Write an application case study with network design diagram including the following topics: - IoT -...
Write an application case study with network design diagram including the following topics: - IoT - Bluetooth - Fog Computing - Redundant - Resilient and measures of resilience - Troubleshooting with half split and move method Highlight in bold each of the above keywords.
How does network development relate to the work breakdown schedule (WBS)? how is the WBS related...
How does network development relate to the work breakdown schedule (WBS)? how is the WBS related to project network development? How can the project manager reduce problems when integrating the work package and the network? Describe how the project manager can eliminate problems during the integration.
Explain the logic used to determine which activity to reduce on a Project Network based on...
Explain the logic used to determine which activity to reduce on a Project Network based on the cost slope and other relevant information.
11. Write an application case study with network design diagram including the following topics: [10 Marks]...
11. Write an application case study with network design diagram including the following topics: [10 Marks] - IoT - Bluetooth - Fog Computing - Redundant - Resilient and measures of resilience - Troubleshooting with half split and move method Highlight in bold each of the above keywords.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT